['Air Programs']
['Hazardous Air Pollutants']
02/27/2022
...
§63.880 Applicability.
(a) The requirements of this subpart apply to the owner or operator of each wool fiberglass manufacturing facility that is an area source or is located at a facility that is an area source.
(b) The requirements of this subpart apply to emissions of chromium compounds, as measured according to the methods and procedures in this subpart, emitted from each new and existing gas-fired glass-melting furnace located at a wool fiberglass manufacturing facility that is an area source.
(c) The provisions of subpart A of this part that apply and those that do not apply to this subpart are specified in Table 1 to this subpart.
(d) Gas-fired glass-melting furnaces that are not subject to subpart NNN of this part are subject to this subpart.
(e) Gas-fired glass-melting furnaces using electricity as a supplemental energy source are subject to this subpart.
§63.881 Definitions.
Terms used in this subpart are defined in the Clean Air Act, in §63.2, or in this section as follows:
Bag leak detection system means systems that include, but are not limited to, devices using triboelectric, light scattering, and other effects to monitor relative or absolute particulate matter emissions.
Gas-fired glass-melting furnace means a unit comprising a refractory vessel in which raw materials are charged, melted at high temperature using natural gas and other fuels, refined, and conditioned to produce molten glass. The unit includes foundations, superstructure and retaining walls, raw material charger systems, heat exchangers, exhaust system, refractory brick work, fuel supply and electrical boosting equipment, integral control systems and instrumentation, and appendages for conditioning and distributing molten glass to forming processes. The forming apparatus, including flow channels, is not considered part of the gas-fired glass-melting furnace. Cold-top electric glass-melting furnaces as defined in subpart NNN of this part are not gas-fired glass-melting furnaces.
Glass pull rate means the mass of molten glass that is produced by a single glass-melting furnace or that is used in the manufacture of wool fiberglass at a single manufacturing line in a specified time period.
Incinerator means an enclosed air pollution control device that uses controlled flame combustion to convert combustible materials to noncombustible gases. For the purposes of this subpart, the term “incinerator” means “regenerative thermal oxidizer”.
Manufacturing line means the manufacturing equipment for the production of wool fiberglass that consists of a forming section where molten glass is fiberized and a fiberglass mat is formed and which may include a curing section where binder resin in the mat is thermally set and a cooling section where the mat is cooled.
New source means any affected source the construction or reconstruction of which is commenced after April 15, 2013.
Wool fiberglass means insulation materials composed of glass fibers made from glass produced or melted at the same facility where the manufacturing line is located.
Wool fiberglass manufacturing facility means any facility manufacturing wool fiberglass.
§63.882 Emission standards.
(a) Emission limits for gas-fired glass-melting furnaces. For each existing, new, or reconstructed gas-fired glass-melting furnace, on and after the compliance date specified in §63.887 whichever date is earlier, you must not discharge or cause to be discharged into the atmosphere emissions in excess of 0.00025 lb of chromium compounds per ton of glass pulled (0.25 lb per thousand tons glass pulled).
(b) Operating limits. On and after the date on which the performance test required by §§63.7 and 63.1384 is completed, you must operate all affected control equipment and processes according to the following requirements.
(1)(i) You must initiate corrective action within one hour of an alarm from a bag leak detection system and complete corrective actions in a timely manner according to the procedures in the operations, maintenance, and monitoring plan.
(ii) You must implement a Quality Improvement Plan consistent with the compliance assurance monitoring provisions of 40 CFR part 64, subpart D when the bag leak detection system alarm is sounded for more than 5 percent of the total operating time in a 6-month block reporting period.
(2)(i) You must initiate corrective action within one hour when any 3-hour block average of the monitored electrostatic precipitator (ESP) parameter is outside the limit(s) established during the performance test as specified in §63.884 and complete corrective actions in a timely manner according to the procedures in the operations, maintenance, and monitoring plan.
(ii) You must implement a Quality Improvement Plan consistent with the compliance assurance monitoring provisions of 40 CFR part 64, subpart D when the monitored ESP parameter is outside the limit(s) established during the performance test as specified in §63.884 for more than 5 percent of the total operating time in a 6-month block reporting period.
(iii) You must operate the ESP such that the monitored ESP parameter is not outside the limit(s) established during the performance test as specified in §63.884 for more than 10 percent of the total operating time in a 6-month block reporting period.
(3)(i) You must initiate corrective action within one hour when any 3-hour block average value for the monitored parameter(s) for a gas-fired glass-melting furnace, which uses no add-on controls, is outside the limit(s) established during the performance test as specified in §63.884 and complete corrective actions in a timely manner according to the procedures in the operations, maintenance, and monitoring plan.
(ii) You must implement a Quality Improvement Plan consistent with the compliance assurance monitoring provisions of 40 CFR part 64, r40CFR63SubpartNNN when the monitored parameter(s) is outside the limit(s) established during the performance test as specified in §63.884 for more than 5 percent of the total operating time in a 6-month block reporting period.
(iii) You must operate a gas-fired glass-melting furnace, which uses no add-on technology, such that the monitored parameter(s) is not outside the limit(s) established during the performance test as specified in §63.884 for more than 10 percent of the total operating time in a 6-month block reporting period.
(4)(i) You must initiate corrective action within one hour when the average glass pull rate of any 4-hour block period for gas-fired glass-melting furnaces equipped with continuous glass pull rate monitors, or daily glass pull rate for glass-melting furnaces not so equipped, exceeds the average glass pull rate established during the performance test as specified in §63.884, by greater than 20 percent and complete corrective actions in a timely manner according to the procedures in the operations, maintenance, and monitoring plan.
(ii) You must implement a Quality Improvement Plan consistent with the compliance assurance monitoring provisions of 40 CFR part 64, subpart D when the glass pull rate exceeds, by more than 20 percent, the average glass pull rate established during the performance test as specified in §63.884 for more than 5 percent of the total operating time in a 6-month block reporting period.
(iii) You must operate each gas-fired glass-melting furnace such that the glass pull rate does not exceed, by more than 20 percent, the average glass pull rate established during the most recent successful performance test as specified in §63.884 for more than 10 percent of the total operating time in a 6-month block reporting period.
(5)(i) You must initiate corrective action within one hour when the average pH (for a caustic scrubber) or pressure drop (for a venturi scrubber) for any 3-hour block period is outside the limits established during the performance tests as specified in §63.884 for each wet scrubbing control device and complete corrective actions in a timely manner according to the procedures in the operations, maintenance, and monitoring plan.
(ii) You must implement a Quality Improvement Plan consistent with the compliance assurance monitoring provisions of 40 CFR part 64, subpart D when any scrubber parameter is outside the limit(s) established during the performance test as specified in §63.884 for more than 5 percent of the total operating time in a 6-month block reporting period.
(iii) You must operate each scrubber such that each monitored parameter is not outside the limit(s) established during the performance test as specified in §63.884 for more than 10 percent of the total operating time in a 6-month block reporting period.
§63.883 Monitoring requirements.
You must meet all applicable monitoring requirements contained in subpart NNN of this part.
§63.884 Performance test requirements.
(a) If you are subject to the provisions of this subpart you must conduct a performance test to demonstrate compliance with the applicable emission limits in §63.882. For existing sources, compliance is demonstrated when the emission rate of the pollutant is equal to or less than each of the applicable emission limits in §63.882 by July 31, 2017. For new sources compliance is demonstrated when the emission rate of the pollutant is equal to or less than each of the applicable emission limits in §63.882 by January 25, 2016 or 180 days after initial startup, whichever is later. You must conduct the performance test according to the procedures in subpart A of this part and in this section.
(b) You must meet all applicable performance test requirements contained in subpart NNN of this part.
§63.885 Test methods and procedures.
(a) You must use the following methods to determine compliance with the applicable emission limits:
(1) Method 1 at 40 CFR part 60, appendix A-1 for the selection of the sampling port location and number of sampling ports;
(2) Method 2 at 40 CFR part 60, appendix A-1 for volumetric flow rate;
(3) Method 3 or 3A (40 CFR part 60, appendix A-2) for oxygen and carbon dioxide for diluent measurements needed to correct the concentration measurements to a standard basis;
(4) Method 4 at 40 CFR part 60, appendix A-4 for moisture content of the stack gas;
(5) Method 29 (40 CFR part 60, appendix A-8) for the concentration of chromium compounds. Each run must consist of a minimum sample volume of two dry standard cubic meters.
(6) An alternative method, subject to approval by the Administrator.
(b) Each performance test must consist of three runs. You must use the average of the three runs in the applicable equation for determining compliance.
§63.886 Notification, recordkeeping, and reporting requirements.
You must meet all applicable notification, recordkeeping and reporting requirements contained in subpart NNN of this part.
§63.887 Compliance dates.
(a) Compliance dates. The owner or operator subject to the provisions of this subpart must be in compliance with the requirements of this subpart by no later than:
(1) Except as noted in paragraph (a)(3) of this section, the compliance date for an owner or operator of an existing source subject to the provisions in this subpart would be July 31, 2017.
(2) Except as noted in paragraph (a)(3) of this section, the compliance date for new and reconstructed sources is upon initial startup of a new gas-fired glass-melting furnace or on July 29, 2015, whichever is later.
(3) The compliance date for the provisions related to the electronic reporting provisions of §63.886 is on July 29, 2015.
(b) Compliance extension. The owner or operator of an existing source subject to this subpart may request from the Administrator an extension of the compliance date for the emission standards for one additional year if such additional period is necessary for the installation of controls. You must submit a request for an extension according to the procedures in §63.6(i)(3).
§63.888 Startups and shutdowns.
You must meet all applicable startup and shutdown provisions contained in subpart NNN of this part.
§§63.889-63.899 [Reserved]
Table 1 to Subpart NN of Part 63 - Applicability of General Provisions (40 CFR Part 63, Subpart A) to Subpart NN
General provisions citation | Requirement | Applies to subpart NN | Explanation |
---|---|---|---|
§63.1(a)(1)-(5) | Applicability | Yes | |
§63.1(a)(6) | Yes | ||
§63.1(a)(7)-(9) | No | [Reserved]. | |
§63.1(a)(10)-(12) | Yes | ||
§63.1(b)(1) | Initial Applicability Determination | Yes | |
§63.1(b)(2) | No | [Reserved]. | |
§63.1(b)(3) | Yes | ||
§63.1(c)(1)-(2) | Yes | ||
§63.1(c)(3)-(4) | No | [Reserved]. | |
§63.1(c)(5)-(e) | Yes | ||
§63.2 | Definitions | Yes | Additional definitions in §63.881. |
§63.3 | Units and Abbreviations | Yes | |
§63.4(a)(1)-(2) | Prohibited Activities | Yes | |
§63.4(a)(3)-(5) | No | [Reserved]. | |
§63.4(b)-(c) | Yes | ||
§63.5(a)-(b)(2) | Construction/Reconstruction Applicability | Yes | |
§63.5(b)(3)-(4) | Yes | ||
§63.5(b)(5) | No | [Reserved]. | |
§63.5(b)(6) | Yes | ||
§63.5(c) | No | [Reserved]. | |
§63.5(d) | Application for Approval of Construction/Reconstruction | Yes | |
§63.5(e) | Approval of Construction/Reconstruction | Yes | |
§63.5(f) | Approval of Construction/Reconstruction Based on State Review | Yes | |
§63.6(a)-(d) | Compliance with Standards and Maintenance Requirements | Yes | |
§63.6(e)(1)(i) | General Duty to Minimize Emissions | No | See §63.882 for general duty requirements. |
§63.6(e)(1)(ii) | Requirement to Correct Malfunctions As Soon As Possible | No | |
§63.6(e)(1)(iii) | Yes | ||
§63.6(e)(2) | No | [Reserved]. | |
§63.6(e)(3) | Startup, Shutdown, and Malfunction (SSM) Plan | No | Startups and shutdowns addressed in §63.888. |
§63.6(f)(1) | SSM Exemption | No | |
§63.6(f)(2)-(3) | Methods for Determining Compliance | Yes | |
§63.6(g) | Use of an Alternative Nonopacity Emission | Yes | |
§63.6(h)(1) | SSM Exemption | No | |
§63.6(h)(2)-(j) | Yes | ||
§63.7(a)-(d) | Yes | §63.884 has specific requirements. | |
§63.7(e)(1) | Performance Testing | No | See §63.882. |
§63.7(e)(2)-(4) | Yes | ||
§63.7(f) | Alternative Test Method | Yes | |
§63.7(g)(1) | Data Analysis | Yes | |
§63.7(g)(2) | No | [Reserved]. | |
§63.7(g)(3) | Yes | ||
§63.7(h) | Waiver of Performance Test | Yes | |
§63.8(a)-(b) | Monitoring Requirements | Yes | |
§63.8(c)(1)(i) | General Duty to Minimize Emissions and CMS Operation | No | See §63.882(b) for general duty requirement. |
§63.8(c)(1)(ii) | Yes | ||
§63.8(c)(1)(iii) | Requirement to Develop SSM Plan for CMS | No | |
§63.8(c)(2)-(d)(2) | Yes | ||
§63.8(d)(3) | Written Procedures for CMS | Yes, except for last sentence, which refers to SSM plan. SSM plans are not required | |
§63.8(e)-(g) | Yes | ||
§63.9(a) | Notification Requirements | Yes | |
§63.9(b)(1)-(2) | Initial Notifications | Yes | |
§63.9(b)(3) | No | [Reserved]. | |
§63.9(b)(4)-(5) | Yes | ||
§63.9(c)-(j) | Yes | ||
§63.10(a) | Recordkeeping and Reporting-Requirements | Yes | |
§63.10(b)(1) | General Recordkeeping Requirements | Yes | |
§63.10(b)(2)(i) | Recordkeeping of Occurrence and Duration of Startups and Shutdowns | No | |
§63.10(b)(2)(ii) | Recordkeeping of Malfunctions | No | See §63.886 for recordkeeping of occurrence and duration of malfunctions and recordkeeping of actions taken during malfunction. |
§63.10(b)(2)(iii) | Maintenance Records | Yes | |
§63.10(b)(2)(iv)-(v) | Actions Taken to Minimize Emissions During SSM | No | |
§63.10(b)(2)(vi) | Recordkeeping for CMS Malfunctions | Yes | |
§63.10(b)(2)(vii)-(xiv) | Other CMS Requirements | Yes | |
§63.10(b)(3) | Recordkeeping Requirement for Applicability Determinations | Yes | |
§63.10(c)(1)-(6) | Additional Recordkeeping Requirements for Sources with CMS | Yes | |
§63.10(c)(7)-(8) | Additional Recordkeeping Requirements for CMS - Identifying Exceedances and Excess Emissions | Yes | |
§63.10(c)(9) | No | [Reserved]. | |
§63.10(c)(10)-(11) | No | See §63.886 for recordkeeping of malfunctions. | |
§63.10(c)(12)-(14) | Yes | ||
§63.10(c)(15) | Use of SSM Plan | No | |
§63.10(d)(1)-(4) | General Reporting Requirements | Yes | |
§63.10(d)(5) | SSM Reports | No | See §63.886(c)(2) for reporting of malfunctions. |
§63.10(e)-(f) | Additional CMS Reports Excess Emission/CMS Performance Reports COMS Data Reports Recordkeeping/Reporting Waiver | Yes | |
§63.11(a)-(b) | Control Device Requirements Applicability Flares | No | Flares will not be used to comply with the emissions limits. |
§63.11(c) | Alternative Work Practice for Monitoring Equipment for Leaks | Yes | |
§63.11(d) | Alternative Work Practice Standard | Yes | |
§63.11(e) | Alternative Work Practice Requirements | Yes | |
§63.12 | State Authority and Delegations | Yes | |
§63.13 | Addresses | Yes | |
§63.14 | Incorporation by Reference | Yes | |
§63.15 | Information Availability/Confidentiality | Yes | |
§63.16 | Performance Track Provisions | Yes |
Source: 80 FR 45325, July 29, 2015, unless otherwise noted.
READ MORESHOW LESS
['Air Programs']
['Hazardous Air Pollutants']
Load More
J. J. Keller is the trusted source for DOT / Transportation, OSHA / Workplace Safety, Human Resources, Construction Safety and Hazmat / Hazardous Materials regulation compliance products and services. J. J. Keller helps you increase safety awareness, reduce risk, follow best practices, improve safety training, and stay current with changing regulations.
Copyright 2024 J. J. Keller & Associate, Inc. For re-use options please contact copyright@jjkeller.com or call 800-558-5011.