Table 1 to Subpart AAAAA of Part 63 - Emission Limits
As required in §63.7090(a), you must meet each emission limit in the following table that applies to you, except for kilns and coolers during startup and shutdown (see table 2 to this subpart for emission limits for kilns and coolers during startup and shutdown).
| For . . . | You must meet the following emission limit |
|---|---|
| 1. All existing lime kilns and their associated lime coolers that did not have a wet scrubber installed and operating prior to January 5, 2004 | PM emissions must not exceed 0.12 pounds per ton of stone feed (lb/tsf). |
| 2. All existing lime kilns and their associated lime coolers that have a wet scrubber, where the scrubber itself was installed and operating prior to January 5, 2004 | PM emissions must not exceed 0.60 lb/tsf. If, at any time after January 5, 2004, the kiln changes to a dry control system, then the PM emission limit in item 1 of this table 1 applies, and the kiln is hereafter ineligible for the PM emission limit in item 2 of this table 1 regardless of the method of PM control. |
| 3. All new lime kilns and their associated lime coolers | PM emissions must not exceed 0.10 lb/tsf. |
| 4. All existing and new lime kilns and their associated coolers at your LMP, and you choose to average PM emissions, except that any kiln that is allowed to meet the 0.60 lb/tsf PM emission limit is ineligible for averaging | Weighted average PM emissions calculated according to equation 2 to § 63.7112(f)(1) must not exceed 0.12 lb/tsf (if you are averaging only existing kilns) or 0.10 lb/tsf (if you are averaging only new kilns). If you are averaging existing and new kilns, your weighted average PM emissions must not exceed the weighted average emission limit calculated according to equation 3 to § 63.7112(g), except that no new kiln and its associated cooler considered alone may exceed an average PM emissions limit of 0.10 lb/tsf. |
| 5. New straight rotary lime kilns and their associated coolers producing dolomitic quick lime and/or dead burned dolomitic lime | HCl emissions must not exceed 1.7 lb/ton of lime produced. |
| 6. Existing straight rotary lime kilns and their associated coolers producing dolomitic quick lime and/or dead burned dolomitic lime | HCl emissions must not exceed 2.3 lb/ton of lime produced. |
| 7. New straight rotary lime kilns and their associated coolers producing high-calcium quick lime | HCl emissions must not exceed 0.015 lb/ton of lime produced. |
| 8. Existing straight rotary lime kilns and their associated coolers producing high-calcium quick lime | HCl emissions must not exceed 0.52 lb/ton of lime produced. |
| 9. All preheater rotary lime kilns and their associated coolers producing dolomitic quick lime and/or dead burned dolomitic lime | HCl emissions must not exceed 0.39 lb/ton of lime produced. |
| 10. All preheater rotary lime kilns and their associated coolers producing high-calcium quick lime | HCl emissions must not exceed 0.096 lb/ton of lime produced. |
| 11. All vertical lime kilns and their associated coolers producing dolomitic quick lime and/or dead burned dolomitic lime | HCl emissions must not exceed 0.39 lb/ton of lime produced. |
| 12. All vertical lime kilns and their associated coolers producing high-calcium quick lime | HCl emissions must not exceed 0.021 lb/ton of lime produced. |
| 13. All new lime kilns and their associated coolers | Mercury emissions must not exceed 27 lb/MMton of lime produced. |
| 14. All existing lime kilns and their associated coolers | Mercury emissions must not exceed 34 lb/MMton of lime produced. |
| 15. All lime kilns and their associated coolers | Total Organic HAP emissions must not exceed 2.6 ppmvd @7% O 2 . |
| 16. All lime kilns and their associated coolers | D/F emissions must not exceed 0.037 ng/dscm (TEQ) 1 @7% O 2 . |
| 17. Stack emissions from all PSH operations at a new or existing affected source | PM emissions must not exceed 0.05 grams per dry standard cubic meter (g/dscm). |
| 18. Stack emissions from all PSH operations at a new or existing affected source, unless the stack emissions are discharged through a wet scrubber control device | Emissions must not exceed 7 percent opacity. |
| 19. Fugitive emissions from all PSH operations at a new or existing affected source, except as provided by item 8 of this table 1 | Emissions must not exceed 10 percent opacity. |
| 20. All PSH operations at a new or existing affected source enclosed in a building | All of the individually affected PSH operations must comply with the applicable PM and opacity emission limitations in items 5 through 7 of this table 1, or the building must comply with the following: There must be no VE from the building, except from a vent; and vent emissions must not exceed the stack emissions limitations in items 5 and 6 of this table 1. |
| 21. Each FF that controls emissions from only an individual, enclosed storage bin | Emissions must not exceed 7 percent opacity. |
| 22. Each set of multiple storage bins at a new or existing affected source, with combined stack emissions | You must comply with the emission limits in items 5 and 6 of this table 1. |
| 1 Determined using the toxic equivalency factors listed in Table 2 of Recommended Toxicity Equivalence Factors (TEFs) for Human Health Risk Assessments of 2, 3, 7, 8-Tetrachlorodibenzo-p-dioxin and Dioxin-Like Compounds (incorporated by reference, see § 63.14). When calculating TEQ, zero may be used for congeners that are below the estimated detection level (EDL). | |
[85 FR 44982, July 24, 2020; 89 FR 57757, July 16, 2024]
Table 2 to Subpart AAAAA of Part 63—Startup and Shutdown Emission Limits for Kilns and Coolers
As required in §63.7090(b), on and after the relevant compliance date for your source as specified in §63.7083(e), you must meet each emission limit in the following table that applies to you.
| For . . . | You must meet the following emission limit | You have demonstrated compliance, if after following the requirements in §63.7112 . . . |
|---|---|---|
| 1. All new and existing lime kilns and their associated coolers equipped with an FF or an ESP during each startup | Emissions must not exceed 15 percent opacity (based on startup period block average) | i. Installed, maintained, calibrated and operated a COMS as required by the general provisions of subpart A of this part and according to PS-1 of appendix B to 40 CFR part 60, except as specified in § 63.7113(g)(2); ii. Collected the COMS data at a frequency of at least once every 15 seconds, determining block averages for each startup period and demonstrating for each startup block period the average opacity does not exceed 15 percent. |
| 2. All existing lime kilns and their associated coolers that have a wet scrubber during each startup | See item 2.b of table 3 to this subpart for emission limit | See item 1 of table 6 to this subpart for requirements for demonstrating compliance. |
| 3. All new and existing lime kilns and their associated coolers equipped with an FF or an ESP during shutdown | Emissions must not exceed 15 percent opacity (based on 6-minute average opacity for any 6-minute block period does not exceed 15 percent) | i. Installed, maintained, calibrated and operated a COMS as required by the general provisions of subpart A of this and according to PS-1 of appendix B to 40 CFR part 60, except as specified in § 63.7113(g)(2); ii. Collecting the COMS data at a frequency of at least once every 15 seconds, determining block averages for each 6-minute period and demonstrating for each 6-minute block period the average opacity does not exceed 15 percent. |
| 4. All existing lime kilns and their associated coolers that have a wet scrubber during shutdown | See item 2.b of table 3 to this subpart for emission limit | See item 1 of table 6 to this subpart for requirements for demonstrating compliance. |
| 5. All new and existing lime kilns that use dry sorbent injection or carbon injection during startup and shutdown | When a lime kiln is in startup or shutdown (as defined in § 63.7143), the operating limits for sorbent and/or carbon injection do not apply in table 3 to this subpart, and the lime kiln operator shall ensure that sorbent or carbon injection is in operation until the unit is no longer in startup or shutdown. During startup and shutdown, the control device shall be operated in accordance with manufacturer's recommendations or by a site-specific operating procedure for startup and shutdown events. | |
| 6. All new and existing lime kilns that use a thermal oxidizer during startup and shutdown | 6. When a lime kiln is in startup or shutdown (as defined in § 63.7143), the temperature limits for a thermal oxidizer in table 3 to this subpart do not apply and the lime kiln operator shall ensure that the thermal oxidizer is in operation until the unit is no longer in startup or shutdown. During startup and shutdown, the control device shall be operated in accordance with manufacturer's recommendations or by a site-specific operating procedure for startup and shutdown events. |
[85 FR 44982, July 24, 2020; 89 FR 57757, July 16, 2024]
Table 3 to Subpart AAAAA of Part 63 - Operating Limits
As required in §63.7090(b), you must meet each operating limit in the following table that applies to you, except for kilns and coolers during startup and shutdown (See table 2 to this subpart for operating limits during startup and shutdown).
| For . . . | You must . . . |
|---|---|
| 1. Each lime kiln and each lime cooler (if there is a separate exhaust to the atmosphere from the associated lime cooler) equipped with an FF | Maintain and operate the FF such that the BLDS or PM detector alarm condition does not exist for more than 5 percent of the total operating time in a 6-month period; and comply with the requirements in § 63.7113(d) through (f) and table 6 to this subpart. In lieu of a BLDS or PM detector maintain the FF such that the 6-minute average opacity for any 6-minute block period does not exceed 15 percent; and comply with the requirements in § 63.7113(f) and (g) and table 6 to this subpart. |
| 2. Each lime kiln equipped with a wet scrubber | a. Maintain the 3-hour block exhaust gas stream pressure drop across the wet scrubber greater than or equal to the greater of the pressure drop operating limit established during the most recent performance test for PM and HCl; and b. Maintain the 3-hour block scrubbing liquid flow rate greater than or equal to the greater of the flow rate operating limit established during the most recent performance test for PM and HCl. |
| 3. Each lime kiln equipped with an electrostatic precipitator | Install a PM detector and maintain and operate the ESP such that the PM detector alarm is not activated and alarm condition does not exist for more than 5 percent of the total operating time in a 6-month period, and comply with § 63.7113(e); or, maintain the ESP such that the 6-minute average opacity for any 6-minute block period does not exceed 15 percent, and comply with the requirements in § 63.7113(g); and comply with the requirements in § 63.7113(f) and table 6 to this subpart. |
| 4. Each PSH operation subject to a PM limit which uses a wet scrubber | Maintain the 3-hour block average exhaust gas stream pressure drop across the wet scrubber greater than or equal to the greater of the pressure drop operating limit established during the performance test for PM and HCl; and maintain the 3-hour block average scrubbing liquid flow rate greater than or equal to the greater of the flow rate operating limit established during the performance test for PM and HCl. |
| 5. All affected sources | Prepare a written OM&M plan; the plan must include the items listed in § 63.7100(d) and the corrective actions to be taken when required in table 6 to this subpart. |
| 6. Each emission unit equipped with an add-on air pollution control device | a. Vent captured emissions through a closed system, except that dilution air may be added to emission streams for the purpose of controlling temperature at the inlet to an FF; and b. Operate each capture/collection system according to the procedures and requirements in the OM&M plan. |
| 7. Each lime kiln equipped with dry sorbent injection | Maintain the 3-hour block dry sorbent flow rate greater than or equal to the flow rate operating limit established during the most recent performance test for HCl. |
| 8. Each lime kiln equipped with a thermal oxidizer | Maintain the 3-hour block average combustion chamber temperature greater or equal to the greater of the combustion chamber operating limit established in the most recent performance test for total organic HAP and D/F. |
| 9. Each lime kiln equipped with activated carbon injection | Maintain the 3-hour block activated carbon injection flow rate greater than or equal to the greater of the flow rate operating limit established during the most recent performance test for total organic HAP, D/F, and mercury. |
[85 FR 44983, July 24, 2020; 89 FR 57759, July 16, 2024]
Table 4 to Subpart AAAAA of Part 63 - Initial Compliance With Emission Limits
As required in §63.7114, you must demonstrate initial compliance with each emission limitation that applies to you, according to the following table.
| For . . . | For the following emission limit . . . | You have demonstrated initial compliance, if after following the requirements in §63.7112 . . . |
|---|---|---|
| 1. All new or existing lime kilns and their associated lime coolers (kilns/coolers) | Emission limits as identified in table 1 to this subpart, or a weighted average calculated according to equation 3 to § 63.7112 | The kiln outlet PM, HCl, mercury, and Total Organic HAP, and dioxins and furans emissions (and if applicable, summed with the separate cooler PM emissions), based on the PM emissions measured using Method 5 or 5D in appendix A to 40 CFR part 60, HCl measured using Method 320 or 321 in appendix A to this part, mercury measured using Method 29 or 30B 5D in appendix A to 40 CFR part 60, and the stone feed rate measurement over the period of initial performance test and Total Organic HAP measured using Method 18 5D in appendix A to 40 CFR part 60 and/or Method 320 in appendix A to this part and dioxins and furans measured using Method 23 in appendix A to 40 CFR part 60, do not exceed the emission limit; if the lime kiln is controlled by an FF or ESP and you are opting to monitor PM emissions with a BLDS or PM detector, you have installed and are operating the monitoring device according to the requirements in § 63.7113(d) or (e), respectively; and if the lime kiln is controlled by an FF or ESP and you are opting to monitor PM emissions using a COMS, you have installed and are operating the COMS according to the requirements in § 63.7113(g). If the kiln is equipped with a dry sorbent injection system, you have a record of the dry sorbent and/or carbon injection flow rate operating parameter over the 3-hour performance test during which emissions did not exceed the emissions limitation. If the kiln is equipped with a thermal oxidizer, you have a record of the combustion chamber operating temperature operating parameter over the 3-hour performance test during which emissions did not exceed the emissions limitation. |
| 2. Stack emissions from all PHS operations at a new or existing affected source | PM emissions must not exceed 0.05 g/dscm | The outlet PM emissions, based on Method 5 or Method 17 in appendices A-3 and A-6, respectively, to 40 CFR part 60, over the period of the initial performance test do not exceed 0.05 g/dscm; and if the emission unit is controlled with a wet scrubber, you have a record of the scrubber's pressure drop and liquid flow rate operating parameters over the 3-hour performance test during which emissions did not exceed the emissions limitation. |
| 3. Stack emissions from all PSH operations at a new or existing affected source, unless the stack emissions are discharged through a wet scrubber control device | Emissions must not exceed 7 percent opacity | Each of the thirty 6-minute opacity averages during the initial compliance period, using Method 9 in appendix A-4 to 40 CFR part 60, does not exceed the 7 percent opacity limit. At least thirty 6-minute averages must be obtained. |
| 4. Fugitive emissions from all PSH operations at a new or existing affected source | Emissions must not exceed 10 percent opacity | Each of the 6-minute opacity averages during the initial compliance period, using Method 9 in appendix A-4 to 40 CFR part 60, does not exceed the 10 percent opacity limit. |
| 5. All PSH operations at a new or existing affected source, enclosed in building | All of the individually affected PSH operations must comply with the applicable PM and opacity emission limitations for items 2 through 4 of this table 4, or the building must comply with the following: There must be no VE from the building, except from a vent, and vent emissions must not exceed the emission limitations in items 2 and 3 of this table 4 | All the PSH operations enclosed in the building have demonstrated initial compliance according to the applicable requirements for items 2 through 4 of this table 4; or if you are complying with the building emission limitations, there are no VE from the building according to item 18 of table 5 to this subpart and § 63.7112(k), and you demonstrate initial compliance with applicable building vent emissions limitations according to the requirements in items 2 and 3 of this table 4. |
| 6. Each FF that controls emissions from only an individual storage bin | Emissions must not exceed 7 percent opacity | Each of the ten 6-minute averages during the 1-hour initial compliance period, using Method 9 in appendix A-4 to 40 CFR part 60, does not exceed the 7 percent opacity limit. |
| 7. Each set of multiple storage bins with combined stack emissions | You must comply with emission limitations in items 2 and 3 of this table 4 | You demonstrate initial compliance according to the requirements in items 2 and 3 of this table 4. |
| 8. All new or existing lime kilns and their associated lime coolers (kilns/coolers) | You must meet the emission limitations for HCl, mercury, total organic HAP, and dioxins and furans in items 5 through 16 of table 1 to this subpart | The kiln outlet HCl, mercury, total organic HAP, and D/F emissions (and if applicable, summed with the separate cooler emissions), based on the emissions measured according to table 5 to this subpart over the period of the initial performance test do not exceed the applicable limits in items 5 through 16 of table 1 to this subpart. If the emission unit is controlled with a wet scrubber, during the HCl performance test you have a record of the scrubber's pressure drop and liquid flow rate operating parameters over the performance test during which emissions did not exceed the HCl emissions limitation. If the emission unit is controlled with a dry sorbent injection, during the HCl performance test you have a record of the dry sorbent flow rate operating parameter over the HCl performance test during which emissions did not exceed the HCl emissions limitation. If the emission unit is controlled with a thermal oxidizer, during the total organic HAP and D/F performance test(s) you have a record of the temperature operating parameter over the total organic HAP and D/F performance test during which emissions did not exceed the total organic HAP and D/F emissions limitation(s). If the emission unit is controlled with an activated carbon injection, during the total organic HAP, D/F, and mercury performance test(s) you have a record of the temperature operating parameter over the total organic HAP, D/F, and mercury performance test(s) during which emissions did not exceed the total organic HAP, D/F, and mercury emissions limitation(s). |
[85 FR 44983, July 24, 2020; 89 FR 57757, July 16, 2024]
Table 5 to Subpart AAAAA of Part 63 - Requirements for Performance Tests
As required in §63.7112, you must conduct each performance test in the following table that applies to you.
| For . . . | You must . . . | Using . . . | According to the following requirements . . . |
|---|---|---|---|
| 1. Each lime kiln and each associated lime cooler, if there is a separate exhaust to the atmosphere from the associated lime cooler | Select the location of the sampling ports and the number of traverse points | Method 1 or 1A of appendix A-1 to 40 CFR part 60; and § 63.6(d)(1)(i) | Sampling sites must be located at the outlet of the control device(s) and prior to any releases to the atmosphere. |
| 2. Each lime kiln and each associated lime cooler, if there is a separate exhaust to the atmosphere from the associated lime cooler | Determine velocity and volumetric flow rate | Method 2, 2A, 2C, 2D, 2F, or 2G in appendices A-1 and A-2 to 40 CFR part 60 | Not applicable. |
| 3. Each lime kiln and each associated lime cooler, if there is a separate exhaust to the atmosphere from the associated lime cooler | Conduct gas molecular weight analysis | Method 3, 3A, or 3B in appendix A-2 to 40 CFR part 60 | You may use manual procedures (but not instrumental procedures) of ASME PTC 19.10-1981—Part 10 (see § 63.14 for availability) as an alternative to using Method 3B. |
| 4. Each lime kiln and each associated lime cooler, if there is a separate exhaust to the atmosphere from the associated lime cooler | Measure moisture content of the stack gas | Method 4 in appendix A-3 to 40 CFR part 60 | Not applicable. |
| 5. Each lime kiln and each associated lime cooler, if there is a separate exhaust to the atmosphere from the associated lime cooler, and which uses a negative pressure PM control device | Measure PM emissions | Method 5 in appendix A-3 to 40 CFR part 60 | Conduct the test(s) when the source is operating at representative operating conditions in accordance with § 63.7(e) before the relevant compliance date for your source as specified in §§ 63.7083(e) and 63.7112(b) on and after the relevant compliance date for your source as specified in § 63.7083(e); the minimum sampling volume must be 0.85 dry standard cubic meter (dscm) (30 dry standard cubic foot (dscf)); if there is a separate lime cooler exhaust to the atmosphere, you must conduct the Method 5 test of the cooler exhaust concurrently with the kiln exhaust test. |
| 6. Each lime kiln and each associated lime cooler, if there is a separate exhaust to the atmosphere from the associated lime cooler, and which uses a positive pressure FF or ESP | Measure PM emissions | Method 5D in appendix A-3 to 40 CFR part 60 | Conduct the test(s) when the source is operating at representative operating conditions in accordance with § 63.7(e) before the relevant compliance date for your source as specified in §§ 63.7083(e) and 63.7112(b) on and after the relevant compliance date for your source as specified in § 63.7083(e); If there is a separate lime cooler exhaust to the atmosphere, you must conduct the Method 5 or 5D test of the separate cooler exhaust concurrently with the kiln exhaust test. Refer to item 5 of this table for sampling time and volume requirements. |
| 7. Each lime kiln | Determine the mass rate of stone feed to the kiln during the kiln performance test | Any suitable device | Calibrate and maintain the device according to manufacturer's instructions; the measuring device used must be accurate to within ±5 percent of the mass rate of stone feed over its operating range. |
| 8. Each lime kiln equipped with a wet scrubber | Establish the operating limit for the average gas stream pressure drop across the wet scrubber during the PM and HCl performance test(s) | Data for the gas stream pressure drop measurement device during the kiln performance test | The continuous pressure drop measurement device must be accurate within plus or minus 1 percent; you must collect the pressure drop data during the period of the performance test and determine the operating limit according to § 63.7112(j). |
| 9. Each lime kiln equipped with a wet scrubber | Establish the operating limit for the average liquid flow rate to the scrubber during the PM and HCl performance test(s) | Data from the liquid flow rate measurement device during the kiln performance test | The continuous scrubbing liquid flow rate measuring device must be accurate within plus or minus 1 percent; you must collect the flow rate data during the period of the performance test and determine the operating limit according to § 63.7112(j). |
| 10. Each lime kiln equipped with a FF or ESP that is monitored with a PM detector | Have installed and have operating the BLDS or PM detector prior to the PM performance test | Standard operating procedures incorporated into the OM&M plan | According to the requirements in § 63.7113(d) or (e), respectively. |
| 11. Each lime kiln equipped with a FF or ESP that is monitored with a COMS | Have installed and have operating the COMS prior to the performance test | Standard operating procedures incorporated into the OM&M plan and as required by the general provisions of subpart A of this part and according to PS-1 of appendix B to 40 CFR part 60, except as specified in § 63.7113(g)(2) | According to the requirements in § 63.7113(g). |
| 12. Each stack emission from a PSH operation, vent from a building enclosing a PSH operation, or set of multiple storage bins with combined stack emissions, which is subject to a PM emission limit | Measure PM emissions | Method 5 or Method 17 in appendices A-3 and A-6 to 40 CFR part 60 | The sample volume must be at least 1.70 dscm (60 dscf); for Method 5, if the gas stream being sampled is at ambient temperature, the sampling probe and filter may be operated without heaters; and if the gas stream is above ambient temperature, the sampling probe and filter may be operated at a temperature high enough, but no higher than 121 °C (250 °F), to prevent water condensation on the filter (Method 17 may be used only with exhaust gas temperatures of not more than 250 °F). |
| 13. Each stack emission from a PSH operation, vent from a building enclosing a PSH operation, or set of multiple storage bins with combined stack emissions, which is subject to an opacity limit | Conduct opacity observations | Method 9 in appendix A-4 to 40 CFR part 60 | The test duration must be for at least 3 hours and you must obtain at least thirty, 6-minute averages. |
| 14. Each stack emissions source from a PSH operation subject to a PM or opacity limit, which uses a wet scrubber | Establish the average gas stream pressure drop across the wet scrubber during the PM and HCl performance test(s) | Data for the gas stream pressure drop measurement device during the PSH operation stack performance test | The pressure drop measurement device must be accurate within plus or minus 1 percent; you must collect the pressure drop data during the period of the performance test and determine the operating limit according to § 63.7112(j). |
| 15. Each stack emissions source from a PSH operation subject to a PM or opacity limit, which uses a wet scrubber | Establish the operating limit for the average liquid flow rate to the scrubber during the PM and HCl performance test(s) | Data from the liquid flow rate measurement device during the PSH operation stack performance test | The continuous scrubbing liquid flow rate measuring device must be accurate within plus or minus 1 percent; you must collect the flow rate data during the period of the performance test and determine the operating limit according to § 63.7112(j). |
| 16. Each FF that controls emissions from only an individual, enclosed, new or existing storage bin | Conduct opacity observations | Method 9 in appendix A-4 to 40 CFR part 60 | The test duration must be for at least 1 hour and you must obtain ten 6-minute averages. |
| 17. Fugitive emissions from any PSH operation subject to an opacity limit | Conduct opacity observations | Method 9 in appendix A-4 to 40 CFR part 60 | The test duration must be for at least 3 hours, but the 3-hour test may be reduced to 1 hour if, during the first 1-hour period, there are no individual readings greater than 10 percent opacity and there are no more than three readings of 10 percent during the first 1-hour period. |
| 18. Each building enclosing any PSH operation, that is subject to a VE limit | Conduct VE check | The specifications in § 63.7112(k) | The performance test must be conducted while all affected PSH operations within the building are operating; the performance test for each affected building must be at least 75 minutes, with each side of the building and roof being observed for at least 15 minutes. |
| 19. Each lime kiln | Measure hydrogen chloride | Method 320 or 321 of appendix A to this part or ASTM 6348-12 (Reapproved 2020) 1 2 | The test duration must be at least one hour. HCl must be used for the analyte spiking. For a positive pressure FF or ESP, determine the number of sampling points per the stratification check procedures of section 8.1.2 of Method 7E in appendix A-4 to 40 CFR part 60 using the sample points determined using the procedures of Section 8 of EPA Method 5D. |
| 20. Each lime kiln | Measure mercury | Method 29 or 30B of appendix A-8 to 40 CFR part 60 or ASTM D6784-16 2 | For Method 29 and ASTM D6784-16 2 the test duration must be at least two hours and the sample volume must be at least 1.70 dscm (60 dscf). For Method 30B, the test duration must be at least one hour and the sample volume at least 100 liters. For a positive pressure FF or ESP, use the procedures of Section 8 of EPA Method 5D for sampling points. |
| 21. Each lime kiln | Measure total organic HAP 3 | Method 18 and/or 320 in appendix A to 40 CFR part 60 and/or ASTM D6348-12 (Reapproved 2020) 1 | The test duration must be at least 1 hour. For EPA Method 320 and ASTM D6348-12 (Reapproved 2020), for a positive pressure FF or ESP, determine the number of sampling points per the stratification check procedures of section 8.1.2 of Method 7E using the sample points determined using the procedures of Section 8 of EPA Method 5D. |
| 22. Each lime kiln | Measure dioxins/furans | Method 23 in appendix A-7 to 40 CFR part 60 | The test duration must be at least 3 hours and the must be at least 3 dscm (106 dscf). For a positive pressure FF or ESP, use the procedures of Section 8 of EPA Method 5D for sampling points. |
| 23. Each lime kiln equipped with dry sorbent injection | Establish the operating limit for the dry sorbent flow rate during the HCl performance test | Data for the dry sorbent flow rate device during the HCl performance test | The flow monitor must meet the criteria in § 63.7113(h); you must collect the dry sorbent flow rate data during the period of the HCl performance test and determine the operating limit according to § 63.7112(j). |
| 24. Each lime kiln equipped with a thermal oxidizer | Establish the operating limit for the combustion chamber temperature during the total organic HAP and D/F performance test(s) | Data for the temperature device during the total organic HAP and D/F performance test(s) | The temperature device must meet the criteria in § 63.7113(i); you must collect the temperature data during the period of the total organic HAP and D/F performance test(s) and determine the operating limit according to § 63.7112(j). |
| 25. Each lime kiln equipped with activated carbon injection | Establish the operating limit for the combustion chamber temperature during the total organic HAP, D/F, and mercury performance test(s) | Data for the activated carbon flow rate device during the total organic HAP, D/F, and mercury performance test(s) | The flow monitor must meet the criteria in § 63.7113(h); you must collect the activated carbon flow rate data during the period of the total organic HAP, D/F, and mercury performance test(s)and determine the operating limit according to § 63.7112(j). |
| 1 When using ASTM D6348-12 (Reapproved 2020) the test plan preparation and implementation in the Annexes to ASTM D6348-12 (Reapproved 2020), annexes A1 through A8 are mandatory. In ASTM D6348-12 (Reapproved 2020) Annex A5 (Analyte Spiking Technique), the percent (%) R must be determined for each target analyte (Equation A5.5). In order for the test data to be acceptable for a compound, %R must be 70% ≥ R ≤ 130%. If the %R value does not meet this criterion for a target compound, the test data is not acceptable for that compound and the test must be repeated for that analyte ( i.e., the sampling and/or analytical procedure should be adjusted before a retest). The %R value for each compound must be reported in the test report, and all field measurements must be corrected with the calculated %R value for that compound according to: Reported Results = ((Measured Concentration in Stack))/(%R) × 100. | |||
| 2 Incorporated by reference, see § 63.14. | |||
| 3 Total Organic HAP is the sum of the concentrations of compounds of formaldehyde, acetaldehyde, toluene, benzene, m-xylene, p-xylene, o-xylene, styrene, ethyl benzene, and naphthalene. | |||
[85 FR 44984, July 24, 2020; 89 FR 57757, July 16, 2024]
Table 6 to Subpart AAAAA of Part 63—Continuous Compliance With Operating Limits
As required in §63.7121, you must demonstrate continuous compliance with each operating limit listed in Table 3 to subpart AAAAA that applies to you, according to the following table.
| For . . . | For the following operating limit . . . | You must demonstrate continuous compliance by . . . |
|---|---|---|
| 1. Each lime kiln controlled by a wet scrubber | Maintain the 3-hour block average exhaust gas stream pressure drop across the wet scrubber greater than or equal to the pressure drop operating limit established during the performance test; and maintain the 3-hour block average scrubbing liquid flow rate greater than or equal to the flow rate operating limit established during the performance test | Collecting the wet scrubber operating data according to all applicable requirements in § 63.7113 and reducing the data according to § 63.7113(a); maintaining the 3-hour block average exhaust gas stream pressure drop across the wet scrubber greater than or equal to the pressure drop operating limit established during the performance test; and maintaining the 3-hour block average scrubbing liquid flow rate greater than or equal to the flow rate operating limit established during the performance test (the continuous scrubbing liquid flow rate measuring device must be accurate within ±1% and the continuous pressure drop measurement device must be accurate within ±1%). |
| 2. Each lime kiln or lime cooler equipped with a FF and using a BLDS, and each lime kiln equipped with an ESP or FF using a PM detector | a. Maintain and operate the FF or ESP such that the bag leak or PM detector alarm, is not activated and alarm condition does not exist for more than 5 percent of the total operating time in each 6-month period | i. Operating the FF or ESP so that the alarm on the bag leak or PM detection system is not activated and an alarm condition does not exist for more than 5 percent of the total operating time in each 6-month reporting period; and continuously recording the output from the BLD or PM detection system; and ii. Each time the alarm sounds and the owner or operator initiates corrective actions within 1 hour of the alarm, 1 hour of alarm time will be counted (if the owner or operator takes longer than 1 hour to initiate corrective actions, alarm time will be counted as the actual amount of time taken by the owner or operator to initiate corrective actions); if inspection of the FF or ESP system demonstrates that no corrective actions are necessary, no alarm time will be counted. |
| 3. Each stack emissions source from a PSH operation subject to an opacity limit, which is controlled by a wet scrubber | Maintain the 3-hour block average exhaust gas stream pressure drop across the wet scrubber greater than or equal to the pressure drop operating limit established during the performance test; and maintain the 3-hour block average scrubbing liquid flow rate greater than or equal to the flow rate operating limit established during the performance test | Collecting the wet scrubber operating data according to all applicable requirements in § 63.7113 and reducing the data according to § 63.7113(a); maintaining the 3-hour block average exhaust gas stream pressure drop across the wet scrubber greater than or equal to the pressure drop operating limit established during the performance test; and maintaining the 3-hour block average scrubbing liquid flow rate greater than or equal to the flow rate operating limit established during the performance test (the continuous scrubbing liquid flow rate measuring device must be accurate within ±1% and the continuous pressure drop measurement device must be accurate within ±1%). |
| 4. For each lime kiln or lime cooler equipped with a FF or an ESP that uses a COMS as the monitoring device | a. Maintain and operate the FF or ESP such that the average opacity for any 6-minute block period does not exceed 15 percent | i. Installing, maintaining, calibrating and operating a COMS as required by the general provisions of subpart A of this part and according to PS-1 of appendix B to 40 CFR part 60, except as specified in § 63.7113(g)(2); and ii. Collecting the COMS data at a frequency of at least once every 15 seconds, determining block averages for each 6-minute period and demonstrating for each 6-minute block period the average opacity does not exceed 15 percent. |
| 7. Each lime kiln equipped with dry sorbent and/or activated carbon injection | Maintain the 3-hour block dry sorbent and/or activated carbon flow rate greater than or equal to the stack flow rate operating limit established during the most recent performance test. | Collecting the dry sorbent and/or activated carbon injection operating data according to all applicable requirements in § 63.7113 and reducing the data according to § 63.7113(a); maintaining the 3-hour block average injection flow rate greater than or equal to the injection flow rate operating limit established during the performance test. |
| 8. Each lime kiln equipped with a thermal oxidizer | Maintain the 3-hour block average combustion chamber temperature greater or equal to the combustion chamber operating limit established in the most recent performance test | Collecting the thermal oxidizer operating data according to all applicable requirements in § 63.7113 and reducing the data according to § 63.7113(a); maintaining the 3-hour block average combustion chamber temperature greater than or equal to the combustion chamber operating limit established during the performance test. |
[85 FR 44984, July 24, 2020; 89 FR 57757, July 16, 2024]
Table 7 to Subpart AAAAA of Part 63 - Periodic Monitoring for Compliance With Opacity and Visible Emissions Limits
As required in §63.7121 you must periodically demonstrate compliance with each opacity and VE limit that applies to you, according to the following table:
| For . . . | For the following emission limitation . . . | You must demonstrate ongoing compliance . . . |
|---|---|---|
| 1. Each PSH operation subject to an opacity limitation as required in Table 1 to this subpart, or any vents from buildings subject to an opacity limitation | a. 7-10 percent opacity, depending on the PSH operation, as required in Table 1 to this subpart | (i) Conducting a monthly 1-minute VE check of each emission unit in accordance with §63.7121(e); the check must be conducted while the affected source is in operation; (ii) If no VE are observed in 6 consecutive monthly checks for any emission unit, you may decrease the frequency of VE checking from monthly to semi-annually for that emission unit; if VE are observed during any semiannual check, you must resume VE checking of that emission unit on a monthly basis and maintain that schedule until no VE are observed in 6 consecutive monthly checks; |
| (iii) If no VE are observed during the semiannual check for any emission unit, you may decrease the frequency of VE checking from semi-annually to annually for that emission unit; if VE are observed during any annual check, you must resume VE checking of that emission unit on a monthly basis and maintain that schedule until no VE are observed in 6 consecutive monthly checks; and | ||
| (iv) If VE are observed during any VE check, you must conduct a 6-minute test of opacity in accordance with Method 9 of appendix A to part 60 of this chapter; you must begin the Method 9 test within 1 hour of any observation of VE and the 6-minute opacity reading must not exceed the applicable opacity limit. | ||
| 2. Any building subject to a VE limit, according to item 8 of Table 1 to this subpart | a. No VE | (i) Conducting a monthly VE check of the building, in accordance with the specifications in §63.7112(k); the check must be conducted while all the enclosed PSH operations are operating; (ii) The check for each affected building must be at least 5 minutes, with each side of the building and roof being observed for at least 1 minute; |
| (iii) If no VE are observed in 6 consecutive monthly checks of the building, you may decrease the frequency of checking from monthly to semi-annually for that affected source; if VE are observed during any semi-annual check, you must resume checking on a monthly basis and maintain that schedule until no VE are observed in 6 consecutive monthly checks; and | ||
| (iv) If no VE are observed during the semi-annual check, you may decrease the frequency of checking from semi-annually to annually for that affected source; and if VE are observed during any annual check, you must resume checking of that emission unit on a monthly basis and maintain that schedule until no VE are observed in 6 consecutive monthly checks (the source is in compliance if no VE are observed during any of these checks). |
Table 8 to Subpart AAAAA of Part 63—Requirements for Reports
As required in §63.7131, you must submit each report in the following table that applies to you.
| You must submit a . . . | The report must contain . . . | You must submit the report . . . |
|---|---|---|
| 1. Compliance report | a. If there are no deviations from any emission limitations (emission limit, operating limit, opacity limit, and VE limit) that applies to you, a statement that there were no deviations from the emission limitations during the reporting period; | Semiannually according to the requirements in § 63.7131(b). |
| b. If there were no periods during which the CMS, including any operating parameter monitoring system, was out-of-control as specified in § 63.8(c)(7), a statement that there were no periods during which the CMS was out-of-control during the reporting period; | Semiannually according to the requirements in § 63.7131(b). | |
| c. If you have a deviation from any emission limitation (emission limit, operating limit, opacity limit, and VE limit) during the reporting period, the report must contain the information in § 63.7131(d); | Semiannually according to the requirements in § 63.7131(b). | |
| d. If there were periods during which the CMS, including any operating parameter monitoring system, was out-of-control, as specified in § 63.8(c)(7), the report must contain the information in § 63.7131(e); and | Semiannually according to the requirements in § 63.7131(b). | |
| e. Before the relevant compliance date for your source as specified in § 63.7083(e), if you had a startup, shutdown or malfunction during the reporting period and you took actions consistent with your SSMP, the compliance report must include the information in § 63.10(d)(5)(i). On and after the relevant compliance date for your source as specified in § 63.7083(e), if you had a startup, shutdown or malfunction during the reporting period and you failed to meet an applicable standard, the compliance report must include the information in § 63.7131(c)(3). | Semiannually according to the requirements in § 63.7131(b). | |
| 2. Before the relevant compliance date for your source as specified in § 63.7083(e), an immediate startup, shutdown, and malfunction report if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your SSMP | Actions taken for the event | By fax or telephone within 2 working days after starting actions inconsistent with the SSMP. |
| 3. Before the relevant compliance date for your source as specified in § 63.7083(e), an immediate startup, shutdown, and malfunction report if you had a startup, shutdown, or malfunction during the reporting period that is not consistent with your SSMP | The information in § 63.10(d)(5)(ii) | By letter within 7 working days after the end of the event unless you have made alternative arrangements with the permitting authority. See § 63.10(d)(5)(ii). |
| 4. Performance Test Report | The information required in § 63.7(g) and § 63.7112(h) | According to the requirements of § 63.7131. |
[85 FR 44985, July 24, 2020; 89 FR 57757, July 16, 2024]
Table 9 to Subpart AAAAA of Part 63—Emissions Averaging Emission Limits
As required in §63.7090(d), if you are using emissions averaging for either HCl emission limits or mercury emission limits you must meet each emission limit in the following table that applies to you.
| For . . . | You must meet the following emission limit |
|---|---|
| 1. Existing straight rotary lime kilns and their associated coolers producing dolomitic quick lime and/or dead burned dolomitic lime | HCl emissions must not exceed 2.1 lb/ton of lime produced. |
| 2. Existing straight rotary lime kilns and their associated coolers producing high-calcium quick lime | HCl emissions must not exceed 0.047 lb/ton of lime produced. |
| 3. Existing preheater rotary lime kilns and their associated coolers producing dolomitic quick lime and/or dead burned dolomitic lime | HCl emissions must not exceed 0.36 lb/ton of lime produced. |
| 4. Existing preheater rotary lime kilns and their associated coolers producing high-calcium quick lime | HCl emissions must not exceed 0.087 lb/ton of lime produced. |
| 5. All vertical lime kilns and their associated coolers producing dolomitic quick lime and/or dead burned dolomitic lime | HCl emissions must not exceed 0.36 lb/ton of lime produced. |
| 6. All vertical lime kilns and their associated coolers producing high-calcium quick lime | HCl emissions must not exceed 0.019 lb/ton of lime produced. |
| 7. Existing lime kilns and their associated coolers | Mercury emissions must not exceed 31 lb/MMton of lime produced. |
[89 FR 57765, July 16, 2024]
Table 10 to Subpart AAAAA of Part 63—Applicability of General Provisions to Subpart AAAAA
As required in §63.7140, you must comply with the applicable General Provisions requirements according to the following table.
| Citation | Summary of requirement | Am I subject to this requirement? | Explanations |
|---|---|---|---|
| § 63.1(a)(1) through (4) | Applicability | Yes | |
| § 63.1(a)(5) | No | ||
| § 63.1(a)(6) | Applicability | Yes | |
| § 63.1(a)(7) through (9) | No | ||
| § 63.1(a)(10) through (14) | Applicability | Yes | |
| § 63.1(b)(1) | Initial Applicability Determination | Yes | §§ 63.7081 and 63.7142 specify additional applicability determination requirements. |
| § 63.1(b)(2) | No | ||
| § 63.1(b)(3) | Initial Applicability Determination | Yes | |
| § 63.1(c)(1) | Applicability After Standard Established | Yes | |
| § 63.1(c)(2) | Permit Requirements | No | Area sources not subject to this subpart, except all sources must make initial applicability determination. |
| § 63.1(c)(3) and (4) | No | ||
| § 63.1(c)(5) | Area Source Becomes Major | Yes | |
| § 63.1(c)(6) | Reclassification | Yes | |
| § 63.1(d) | No | ||
| § 63.1(e) | Applicability of Permit Program | Yes | |
| § 63.2 | Definitions | Yes | Additional definitions in § 63.7143. |
| § 63.3(a) through (c) | Units and Abbreviations | Yes | |
| § 63.4(a)(1) and (2) | Prohibited Activities | Yes | |
| § 63.4(a)(3) through (5) | No | ||
| § 63.4(b) and (c) | Circumvention, Severability | Yes | |
| § 63.5(a)(1) and (2) | Construction/Reconstruction | Yes | |
| § 63.5(b)(1) | Compliance Dates | Yes | |
| § 63.5(b)(2) | No | ||
| § 63.5(b)(3) and (4) | Construction Approval, Applicability | Yes | |
| § 63.5(b)(5) | No | ||
| § 63.5(b)(6) | Applicability | Yes | |
| § 63.5(c) | No | ||
| § 63.5(d)(1) through (4) | Approval of Construction/Reconstruction | Yes | |
| § 63.5(e) | Approval of Construction/Reconstruction | Yes | |
| § 63.5(f)(1) and (2) | Approval of Construction/Reconstruction | Yes | |
| § 63.6(a) | Compliance for Standards and Maintenance | Yes | |
| § 63.6(b)(1) through (5) | Compliance Dates | Yes | |
| § 63.6(b)(6) | No | ||
| § 63.6(b)(7) | Compliance Dates | Yes | |
| § 63.6(c)(1) and (2) | Compliance Dates | Yes | |
| § 63.6(c)(3) and (4) | No | ||
| § 63.6(c)(5) | Compliance Dates | Yes | |
| § 63.6(d) | No | ||
| § 63.6(e)(1)(i) | General Duty to Minimize Emissions | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7100 for general duty requirement. |
| § 63.6(e)(1)(ii) | Requirement to Correct Malfunctions ASAP | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | |
| § 63.6(e)(1)(iii) | Operation and Maintenance Requirements | Yes | |
| § 63.6(e)(2) | No | [Reserved]. | |
| § 63.6(e)(3) | Startup, Shutdown Malfunction Plan | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | On and after the relevant compliance date for your source as specified in § 63.7083(e), the OM&M plan must address periods of startup and shutdown. See § 63.7100(d). |
| § 63.6(f)(1) | SSM exemption | No | See § 63.7100. For periods of startup and shutdown, see § 63.7090(c). |
| § 63.6(f)(2) and (3) | Methods for Determining Compliance | Yes | |
| § 63.6(g)(1) through (3) | Alternative Standard | Yes | |
| § 63.6(h)(1) | SSM exemption | No | See § 63.7100. For periods of startup and shutdown, see § 63.7090(c). |
| § 63.6(h)(2) | Methods for Determining Compliance | Yes | |
| § 63.6(h)(3) | No | ||
| § 63.6(h)(4) through (h)(5)(i) | Opacity/VE Standards | Yes | This requirement only applies to opacity and VE performance checks required in table 5 to this subpart. |
| § 63.6(h)(5)(ii) and (iii) | Opacity/VE Standards | No | Test durations are specified in this subpart; this subpart takes precedence. |
| § 63.6(h)(5)(iv) | Opacity/VE Standards | No | |
| § 63.6(h)(5)(v) | Opacity/VE Standards | Yes | |
| § 63.6(h)(6) | Opacity/VE Standards | Yes | |
| § 63.6(h)(7) | COM Use | Yes | |
| § 63.6(h)(8) | Compliance with Opacity and VE | Yes | |
| § 63.6(h)(9) | Adjustment of Opacity Limit | Yes | |
| § 63.6(i)(1) through (14) | Extension of Compliance | Yes | |
| § 63.6(i)(15) | No | ||
| § 63.6(i)(16) | Extension of Compliance | Yes | |
| § 63.6(j) | Exemption from Compliance | Yes | |
| § 63.7(a)(1) through (3) | Performance Testing Requirements | Yes | § 63.7110 specifies deadlines; § 63.7112 has additional specific requirements. |
| § 63.7(b) | Notification | Yes | |
| § 63.7(c) | Quality Assurance/Test Plan | Yes | |
| § 63.7(d) | Testing Facilities | Yes | |
| § 63.7(e)(1) | Conduct of Tests | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7112(b). |
| § 63.7(e)(2) through (4) | Conduct of Tests | Yes | |
| § 63.7(f) | Alternative Test Method | Yes | |
| § 63.7(g) | Data Analysis | Yes | |
| § 63.7(h) | Waiver of Tests | Yes | |
| § 63.8(a)(1) | Monitoring Requirements | Yes | See § 63.7113. |
| § 63.8(a)(2) | Monitoring | Yes | |
| § 63.8(a)(3) | No | ||
| § 63.8(a)(4) | Monitoring | No | Flares not applicable. |
| § 63.8(b)(1) through (3) | Conduct of Monitoring | Yes | |
| § 63.8(c)(1)(i) | CMS Operation/Maintenance | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7100 for OM&M requirements. |
| § 63.8(c)(1)(ii) | CMS Spare Parts | Yes | |
| § 63.8(c)(1)(iii) | Requirement to Develop SSM Plan for CMS | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | On and after the relevant compliance date for your source as specified in § 63.7083(e), no longer required. |
| § 63.8(c)(2) and (3) | CMS Operation/Maintenance | Yes | |
| § 63.8(c)(4) | CMS Requirements | No | See § 63.7121. |
| § 63.8(c)(4)(i) and (ii) | Cycle Time for COM and CEMS | Yes | No CEMS are required under this subpart; see § 63.7113 for CPMS requirements. |
| § 63.8(c)(5) | Minimum COM procedures | Yes | COM not required. |
| § 63.8(c)(6) | CMS Requirements | No | See § 63.7113. |
| § 63.8(c)(7) and (8) | CMS Requirements | Yes | |
| § 63.8(d)(1) and (2) | Quality Control | Yes | See also § 63.7113. |
| § 63.8(d)(3) | Quality Control | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | |
| § 63.8(e) | Performance Evaluation for CMS | Yes | See also § 63.7113. |
| § 63.8(f)(1) through (5) | Alternative Monitoring Method | Yes | |
| § 63.8(f)(6) | Alternative to Relative Accuracy Test for CEMS | No | No CEMS required in this subpart. |
| § 63.8(g)(1) through (5) | Data Reduction; Data That Cannot Be Used | No | See data reduction requirements in §§ 63.7120 and 63.7121. |
| § 63.9(a) | Notification Requirements | Yes | See § 63.7130. |
| § 63.9(b) | Initial Notifications | Yes | |
| § 63.9(c) | Request for Compliance Extension | Yes | |
| § 63.9(d) | New Source Notification for Special Compliance Requirements | Yes | |
| § 63.9(e) | Notification of Performance Test | Yes | |
| § 63.9(f) | Notification of VE/Opacity Test | Yes | This requirement only applies to opacity and VE performance tests required in table 5 to this subpart. Notification not required for VE/opacity test under table 7 to this subpart. |
| § 63.9(g) | Additional CMS Notifications | No | Not required for operating parameter monitoring. |
| § 63.9(h)(1) through (3) | Notification of Compliance Status | Yes | |
| § 63.9(h)(4) | No | ||
| § 63.9(h)(5) and (6) | Notification of Compliance Status | Yes | |
| § 63.9(i) | Adjustment of Deadlines | Yes | |
| § 63.9(j) | Change in Previous Information | Yes | |
| § 63.9(k) | Electronic reporting procedures | Yes | Only as specified in § 63.9(j). |
| § 63.10(a) | Recordkeeping/Reporting General Requirements | Yes | See §§ 63.7131 through 63.7133. |
| § 63.10(b)(1) | Records | Yes | |
| § 63.10(b)(2)(i) | Recordkeeping of Occurrence and Duration of Startups and Shutdowns | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | |
| § 63.10(b)(2)(ii) | Recordkeeping of Failures to Meet a Standard | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7132 for recordkeeping of (1) date, time and duration; (2) listing of affected source or equipment, and an estimate of the quantity of each regulated pollutant emitted over the standard; and (3) actions to minimize emissions and correct the failure. |
| § 63.10(b)(2)(iii) | Maintenance Records | Yes | |
| § 63.10(b)(2)(iv) and (v) | Actions Taken to Minimize Emissions During SSM | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7100 for OM&M requirements. |
| § 63.10(b)(2)(vi) through (xii) | Recordkeeping for CMS | Yes | |
| § 63.10(b)(2)(xiii) | Records for Relative Accuracy Test | No | |
| § 63.10(b)(2)(xiv) | Records for Notification | Yes | |
| § 63.10(b)(3) | Applicability Determinations | Yes | |
| § 63.10(c) | Additional CMS Recordkeeping | No | See § 63.7132. |
| § 63.10(d)(1) | General Reporting Requirements | Yes | |
| § 63.10(d)(2) | Performance Test Results | Yes | |
| § 63.10(d)(3) | Opacity or VE Observations | Yes | For the periodic monitoring requirements in table 7 to this subpart, report according to § 63.10(d)(3) only if VE observed and subsequent visual opacity test is required. |
| § 63.10(d)(4) | Progress Reports | Yes | |
| § 63.10(d)(5)(i) | Periodic Startup, Shutdown, Malfunction Reports | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | On and after the relevant compliance date for your source as specified in § 63.7083(e), see § 63.7131 for malfunction reporting requirements. |
| § 63.10(d)(5)(ii) | Immediate Startup, Shutdown, Malfunction Reports | Yes before the relevant compliance date for your source as specified in § 63.7083(e) No on and after the relevant compliance date for your source as specified in § 63.7083(e) | |
| § 63.10(e) | Additional CMS Reports | No | See specific requirements in this subpart, see § 63.7131. |
| § 63.10(f) | Waiver for Recordkeeping/Reporting | Yes | |
| § 63.11(a) and (b) | Control Device and Work Practice Requirements | No | Flares not applicable. |
| § 63.12(a) through (c) | State Authority and Delegations | Yes | |
| § 63.13(a) through (c) | State/Regional Addresses | Yes | |
| § 63.14(a) and (b) | Incorporation by Reference | No | |
| § 63.15(a) and (b) | Availability of Information and Confidentiality | Yes | |
| § 63.16 | Performance Track Provisions | Yes |
[89 FR 57766, July 16, 2024]
Table 11 to Subpart AAAAA of Part 63—Toxicity Equivalence Factors (TEFs) for Human Health Risk Assessment of Polychlorinated Dibenzo-p-Dioxins, Dibenzofurans, and Dioxin-Like Polychlorinated Biphenyls
| Dioxin/Furan | 2005 TEFs |
|---|---|
| 2,3,7,8-TCDD | 1 |
| 1,2,3,7,8-PeCDD | 1 |
| 1,2,3,4,7,8-HxCDD | 0.1 |
| 1,2,3,6,7,8-HxCDD | 0.1 |
| 1,2,3,7,8,9-HxCDD | 0.1 |
| 1,2,3,4,6,7,8-HpCDD | 0.01 |
| OCDD | 0.0003 |
| 2,3,7,8-TCDF | 0.1 |
| 1,2,3,7,8-PeCDF | 0.03 |
| 2,3,4,7,8-PeCDF | 0.3 |
| 1,2,3,4,7,8-HxCDF | 0.1 |
| 1,2,3,6,7,8-HxCDF | 0.1 |
| 1,2,3,7,8,9-HxCDF | 0.1 |
| 2,3,4,6,7,8-HxCDF | 0.1 |
| 1,2,3,4,6,7,8-HpCDF | 0.01 |
| 1,2,3,4,7,8,9-HpCDF | 0.01 |
| OCDF | 0.0003 |
| 1 EPA/100/R-10/005, “Recommended Toxicity Equivalence Factors (TEFs) for Human Health Risk Assessments of 2, 3, 7, 8-Tetrachlorodibenzo-p-dioxin and Dioxin-Like Compounds”, December 2010. (See § 63.14 for availability.) | |
[89 FR 57769, July 16, 2024]
Source: 69 FR 416, Jan. 5, 2004, unless otherwise noted.
['Air Programs']
['Hazardous Air Pollutants']
UPGRADE TO CONTINUE READING
J. J. Keller is the trusted source for DOT / Transportation, OSHA / Workplace Safety, Human Resources, Construction Safety and Hazmat / Hazardous Materials regulation compliance products and services. J. J. Keller helps you increase safety awareness, reduce risk, follow best practices, improve safety training, and stay current with changing regulations.
Copyright 2026 J. J. Keller & Associate, Inc. For re-use options please contact copyright@jjkeller.com or call 800-558-5011.