['Air Programs']
['Hazardous Air Pollutants']
02/02/2025
...
Table 1 to Subpart BBBBBB of Part 63 - Applicability Criteria, Emission Limits, and Management Practices for Storage Tanks
If you own or operate . . . | Then you must . . . |
---|---|
1. A gasoline storage tank meeting either of the following conditions: (i) a capacity of less than 75 cubic meters (m 3); or (ii) a capacity of less than 151 m 3 and a gasoline throughput of 480 gallons per day or less. Gallons per day is calculated by summing the current day's throughput, plus the throughput for the previous 364 days, and then dividing that sum by 365 | (a) Equip each gasoline storage tank with a fixed roof that is mounted to the storage tank in a stationary manner, and maintain all openings in a closed position at all times when not in use; and (b) No later than the dates specified in §63.11083all pressure relief devices on each gasoline storage tank must be set to no less than 18 inches of water at all times to minimize breathing losses. |
2. A gasoline storage tank with a capacity of greater than or equal to 75 m 3 and not meeting any of the criteria specified in item 1 of this table | Do the following: (a) Reduce emissions of total organic HAP or TOC by 95 weight-percent with a closed vent system and control device, as specified in §60.112b(a)(3) of this chapter; or (b) Equip each internal floating roof gasoline storage tank according to the requirements in §60.112b(a)(1) of this chapter, except for the secondary seal requirements under §60.112b(a)(1)(ii)(B) and the requirements in §60.112b(a)(1)(iv) through (ix) of this chapter; and (c) No later than the dates specified in §63.11083equip, maintain, and operate each internal floating roof control system to maintain the vapor concentration within the storage tank above the floating roof at or below 25 percent of the LEL on a 5-minute rolling average basis without the use of purge gas, which may require additional controls beyond those specified in item 2(b) of this table; and (d) Equip each external floating roof gasoline storage tank according to the requirements in §60.112b(a)(2) of this chapter, except that the requirements of §60.112b(a)(2)(ii) of this chapter shall only be required if such storage tank does not currently meet the requirements of §60.112b(a)(2)(i) of this chapter; by the dates specified in §63.11083all external floating roofs must meet the requirements of §60.112b(a)(2)(ii) of this chapter; or (e) Equip and operate each internal and external floating roof gasoline storage tank according to the applicable requirements in §63.1063(a)(1) and (b), except for the secondary seal requirements under §63.1063(a)(1)(i)(C) and (D), and equip each external floating roof gasoline storage tank according to the requirements of §63.1063(a)(2) by the dates specified in §63.11087(b) if such storage tank does not currently meet the requirements of §63.1063(a)(1); by the dates specified in §63.11083all external floating roofs must meet the requirements of §63.1063(a)(2); and (f) No later than the dates specified in §63.11083equip, maintain, and operate each internal floating roof control system to maintain the vapor concentration within the storage tank above the floating roof at or below 25 percent of the LEL on a 5-minute rolling average basis without the use of purge gas, which may require additional controls beyond those specified in item 2(e) of this table. |
3. A surge control tank | Equip each tank with a fixed roof that is mounted to the tank in a stationary manner and with a pressure/vacuum vent with a positive cracking pressure of no less than 0.50 inches of water. Maintain all openings in a closed position at all times when not in use. |
[76 FR 4179, Jan. 24, 2011; 89 FR 39344, May 8, 2024]
Table 2 to Subpart BBBBBB of Part 63 - Applicability Criteria, Emission Limits, and Management Practices for Loading Racks
If you own or operate . . . | Then you must . . . |
---|---|
1. A bulk gasoline terminal loading rack(s) with a gasoline throughput (total of all racks) of 250,000 gallons per day, or greater (“large bulk gasoline terminal”). Gallons per day is calculated by summing the current day's throughput, plus the throughput for the previous 364 days, and then dividing that sum by 365 | (a) Equip your loading rack(s) with a vapor collection system designed and operated to collect the TOC vapors displaced from cargo tanks during product loading; and (b) Reduce emissions of TOC to less than or equal to 80 mg/l of gasoline loaded into gasoline cargo tanks at the loading rack; and (c) No later than the dates specified in §63.11083reduce emissions of TOC to the applicable limits in table 3 to this subpart. The requirements in item 1(b) do not apply when demonstrating compliance with this item; and (d) Design and operate the vapor collection system to prevent any TOC vapors collected at one loading rack or lane from passing through another loading rack or lane to the atmosphere; and (e) Limit the loading of gasoline into gasoline cargo tanks that are vapor tight using the procedures specified in §60.502(e) through (j) of this chapter. For the purposes of this section, the term “tank truck” as used in §60.502(e) through (j) means “gasoline cargo tank” as defined in §63.11100and (f) No later than the dates specified in §63.11083limit the loading of liquid product into gasoline cargo tanks using the procedures specified in §60.502a(e) through (i) of this chapter and in §63.11092(g) and (h). The requirements in item 1(e) do not apply when demonstrating compliance with this item. |
2. A bulk gasoline terminal loading rack(s) with a gasoline throughput (total of all racks) of less than 250,000 gallons per day. Gallons per day is calculated by summing the current day's throughput, plus the throughput for the previous 364 days, and then dividing that sum by 365 | (a) Use submerged filling with a submerged fill pipe that is no more than 6 inches from the bottom of the cargo tank; and (b) Make records available within 24 hours of a request by the Administrator to document your gasoline throughput. (c) No later than the dates specified in §63.11083limit the loading of gasoline into gasoline cargo tanks that are vapor tight using the procedures specified in §60.502a(e) of this chapter and in §63.11092(g). |
[76 FR 4179, Jan. 24, 2011; 89 FR 39344, May 8, 2024]
Table 3 to Subpart BBBBBB of Part 63 - Emission Limitations and Requirements for Large Bulk Gasoline Terminals Based on Control System Used
If you operate . . . | Then you must . . . |
---|---|
1. A thermal oxidation system | (a) Reduce emissions of TOC to less than or equal to 35 mg/l of liquid product loaded into gasoline cargo tanks at the loading rack; and (b) Continuously meet the applicable operating limit as specified in §63.11092(e)(2). |
2. A flare | Operate the flare following the applicable requirements specified in §60.502a(c)(3) of this chapter. |
3. A carbon adsorption system, refrigerated condenser, or other vapor recovery system. | (a) Reduce emissions of TOC to less than or equal to 19,200 parts per million by volume as propane determined on a 3-hour rolling average considering all periods when the vapor recovery system is capable of processing gasoline vapors, including periods when liquid product is being loaded, during carbon bed regeneration, and when preparing the beds for reuse. (b) Operate the vapor recovery system to minimize air or nitrogen intrusion except as needed for the system to operate as designed for the purpose of removing VOC from the adsorption media or to break vacuum in the system and bring the system back to atmospheric pressure. Consistent with §63.4the use of diluents to achieve compliance with a relevant standard based on the concentration of a pollutant in the effluent discharged to the atmosphere is prohibited. |
[73 FR 1933, Jan. 10, 2008, as amended at 76 FR 4180, Jan. 24, 2011; 85 FR 73919, Nov.19, 2020; 89 FR 39344, May 8, 2024]
Table 4 to Subpart BBBBBB of Part 63 - Applicability of General Provisions
Citation | Subject | Brief description | Applies to this subpart |
---|---|---|---|
§63.1 | Applicability | Initial applicability determination; applicability after standard established; permit requirements; extensions, notifications | Yes, specific requirements given in §63.11081 |
§63.1(c)(2) | Title V permit | Requirements for obtaining a title V permit from the applicable permitting authority | Yes, §63.11081(b) exempts identified area sources from the obligation to obtain title V operating permits. |
§63.2 | Definitions | Definitions for standards in this part | Yes, additional definitions in §63.11100 |
§63.3 | Units and Abbreviations | Units and abbreviations for standards under this part | Yes. |
§63.4 | Prohibited Activities and Circumvention | Prohibited activities; circumvention, severability | Yes. |
§63.5 | Construction/Reconstruction | Applicability; applications; approvals | Yes. |
§63.6(a) | Compliance with Standards/Operation & Maintenance Applicability | General Provisions apply unless compliance extension; General Provisions apply to area sources that become major | Yes. |
§63.6(b)(1) through (4) | Compliance Dates for New and Reconstructed Sources | Dates standards apply for new and reconstructed sources | Yes. |
§63.6(b)(5) | Notification | Must notify if commenced construction or reconstruction after proposal | Yes. |
§63.6(b)(6) | [Reserved]. | ||
§63.6(b)(7) | Compliance Dates for New and Reconstructed Area Sources that Become Major | Area sources that become major must comply with major source standards immediately upon becoming major, regardless of whether required to comply when they were an area source | No. |
§63.6(c)(1) and (2) | Compliance Dates for Existing Sources | Comply according to date in this subpart | No, §63.11083specifies the compliance dates. |
§63.6(c)(3) and (4) | [Reserved]. | ||
§63.6(c)(5) | Compliance Dates for Existing Area Sources that Become Major | Area sources that become major must comply with major source standards by date indicated in this subpart or by equivalent time period (e.g., 3 years) | No. |
§63.6(d) | [Reserved]. | ||
§63.6(e)(1)(i) | General duty to minimize emissions | Operate to minimize emissions at all times; information Administrator will use to determine if operation and maintenance requirements were met | No. See§63.11085for general duty requirement. |
§63.6(e)(1)(ii) | Requirement to correct malfunctions as soon as possible | Owner or operator must correct malfunctions as soon as possible | No. |
§63.6(e)(2) | [Reserved]. | ||
§63.6(e)(3) | Startup, Shutdown, and Malfunction (SSM) plan | Requirement for SSM plan; content of SSM plan; actions during SSM | No. |
§63.6(f)(1) | Compliance Except During SSM | You must comply with emission standards at all times except during SSM | No. |
§63.6(f)(2) and (3) | Methods for Determining Compliance | Compliance based on performance test, operation and maintenance plans, records, inspection | Yes. |
§63.6(g)(1) through (3) | Alternative Standard | Procedures for getting an alternative standard | Yes. |
§63.6(h)(1) | Compliance with Opacity/VE Standards | You must comply with opacity/VE standards at all times except during SSM | No. |
§63.6(h)(2)(i) | Determining Compliance with Opacity/VE Standards | If standard does not state test method, use EPA Method 9 for opacity in appendix A to part 60 of this chapter and EPA Method 22 for VE in appendix A to part 60 of this chapter | No. |
§63.6(h)(2)(ii) | [Reserved]. | ||
§63.6(h)(2)(iii) | Using Previous Tests to Demonstrate Compliance with Opacity/VE Standards | Criteria for when previous opacity/VE testing can be used to show compliance with this subpart | No. |
§63.6(h)(3) | [Reserved]. | ||
§63.6(h)(4) | Notification of Opacity/VE Observation Date | Must notify Administrator of anticipated date of observation | No. |
§63.6(h)(5)(i) and (iii) through (v) | Conducting Opacity/VE Observations | Dates and schedule for conducting opacity/VE observations | No. |
§63.6(h)(5)(ii) | Opacity Test Duration and Averaging Times | Must have at least 3 hours of observation with 30 6-minute averages | No. |
§63.6(h)(6) | Records of Conditions During Opacity/VE Observations | Must keep records available and allow Administrator to inspect | No. |
§63.6(h)(7)(i) | Report Continuous Opacity Monitoring System (COMS) Monitoring Data from Performance Test | Must submit COMS data with other performance test data | No. |
§63.6(h)(7)(ii) | Using COMS Instead of EPA Method 9 | Can submit COMS data instead of EPA Method 9 results even if this subpart requires EPA Method 9 in appendix A of part 60 of this chapter, but must notify Administrator before performance test | No. |
§63.6(h)(7)(iii) | Averaging Time for COMS During Performance Test | To determine compliance, must reduce COMS data to 6-minute averages | No. |
§63.6(h)(7)(iv) | COMS Requirements | Owner/operator must demonstrate that COMS performance evaluations are conducted according to §63.8(e); COMS are properly maintained and operated according to §63.8(c) and data quality as §63.8(d) | No. |
§63.6(h)(7)(v) | Determining Compliance with Opacity/VE Standards | COMS is probable but not conclusive evidence of compliance with opacity standard, even if EPA Method 9 (in appendix A to part 60 of this chapter) observation shows otherwise. Requirements for COMS to be probable evidence-proper maintenance, meeting Performance Specification 1 in appendix B to part 60 of this chapter, and data have not been altered | No. |
§63.6(h)(8) | Determining Compliance with Opacity/VE Standards | Administrator will use all COMS, EPA Method 9 (in appendix A to part 60 of this chapter), and EPA Method 22 (in appendix A to part 60 of this chapter) results, as well as information about operation and maintenance to determine compliance | No. |
§63.6(h)(9) | Adjusted Opacity Standard | Procedures for Administrator to adjust an opacity standard | No. |
§63.6(i)(1) through (14) | Compliance Extension | Procedures and criteria for Administrator to grant compliance extension | Yes. |
§63.6(j) | Presidential Compliance Exemption | President may exempt any source from requirement to comply with this subpart | Yes. |
§63.7(a)(2) | Performance Test Dates | Dates for conducting initial performance testing; must conduct 180 days after compliance date | Yes. |
§63.7(a)(3) | Section 114 Authority | Administrator may require a performance test under CAA section 114 at any time | Yes. |
§63.7(a)(4) | Force Majeure | Provisions for delayed performance tests due to force majeure | Yes. |
§63.7(b)(1) | Notification of Performance Test | Must notify Administrator 60 days before the test | Yes. |
§63.7(b)(2) | Notification of Re-scheduling | If have to reschedule performance test, must notify Administrator of rescheduled date as soon as practicable and without delay | Yes. |
§63.7(c) | Quality Assurance (QA)/Test Plan | Requirement to submit site-specific test plan 60 days before the test or on date Administrator agrees with; test plan approval procedures; performance audit requirements; internal and external QA procedures for testing | Yes. |
§63.7(d) | Testing Facilities | Requirements for testing facilities | Yes. |
§63.7(e)(1) | Conditions for Conducting Performance Tests | Performance test must be conducted under representative conditions | No, §63.11092(i) specifies conditions for conducting performance tests. |
§63.7(e)(2) | Conditions for Conducting Performance Tests | Must conduct according to this subpart and EPA test methods unless Administrator approves alternative | Yes. |
§63.7(e)(3) | Test Run Duration | Must have three test runs of at least 1 hour each; compliance is based on arithmetic mean of three runs; conditions when data from an additional test run can be used | Yes, except for testing conducted under §63.11092(a) and (e). |
§63.7(f) | Alternative Test Method | Procedures by which Administrator can grant approval to use an intermediate or major change, or alternative to a test method | Yes. |
§63.7(g) | Performance Test Data Analysis | Must include raw data in performance test report; must submit performance test data 60 days after end of test with the notification of compliance status; keep data for 5 years | Yes, except this subpart specifies how and when the performance test and performance evaluation results are reported. |
§63.7(h) | Waiver of Tests | Procedures for Administrator to waive performance test | Yes. |
§63.8(a)(1) | Applicability of Monitoring Requirements | Subject to all monitoring requirements in standard | Yes. |
§63.8(a)(2) | Performance Specifications | Performance specifications in appendix B to part 60 of this chapter apply | Yes. |
§63.8(a)(3) | [Reserved]. | ||
§63.8(a)(4) | Monitoring of Flares | Monitoring requirements for flares in §63.11apply | Yes. |
§63.8(b)(1) | Monitoring | Must conduct monitoring according to standard unless Administrator approves alternative | Yes. |
§63.8(b)(2) and (3) | Multiple Effluents and Multiple Monitoring Systems | Specific requirements for installing monitoring systems; must install on each affected source or after combined with another affected source before it is released to the atmosphere provided the monitoring is sufficient to demonstrate compliance with the standard; if more than one monitoring system on an emission point, must report all monitoring system results, unless one monitoring system is a backup | Yes. |
§63.8(c)(1) introductory text | Monitoring System Operation and Maintenance | Maintain monitoring system in a manner consistent with good air pollution control practices | Yes. |
§63.8(c)(1)(i) | Operation and Maintenance of CMS | Must maintain and operate each CMS as specified in §63.6(e)(1) | No. |
§63.8(c)(1)(ii) | Operation and Maintenance of CMS | Must keep parts for routine repairs readily available | Yes. |
§63.8(c)(1)(iii) | Operation and Maintenance of CMS | Requirement to develop SSM Plan for CMS | No. |
§63.8(c)(2) through (8) | CMS Requirements | Must install to get representative emission or parameter measurements; must verify operational status before or at performance test | Yes. |
§63.8(d)(1) and (2) | CMS Quality Control | Requirements for CMS quality control, including calibration, etc. | Yes. |
§63.8(d)(3) | CMS Quality Control Records | Must keep quality control plan on record for 5 years; keep old versions for 5 years after revisions | No. This subpart specifies CMS records requirements. |
§63.8(e) | CMS Performance Evaluation | Notification, performance evaluation test plan, reports | Yes, except this subpart specifies how and when the performance evaluation results are reported. |
§63.8(f)(1) through (5) | Alternative Monitoring Method | Procedures for Administrator to approve alternative monitoring | Yes. |
§63.8(f)(6) | Alternative to Relative Accuracy Test | Procedures for Administrator to approve alternative relative accuracy tests for CEMS | Yes. |
§63.8(g) | Data Reduction | COMS 6-minute averages calculated over at least 36 evenly spaced data points; CEMS 1 hour averages computed over at least 4 equally spaced data points; data that cannot be used in average | Yes. |
§63.9(a) | Notification Requirements | Applicability and State delegation | Yes. |
§63.9(b)(1), (2), (4), and (5) | Initial Notifications | Submit notification of being subject to standard; notification of intent to construct/reconstruct, notification of commencement of construction/reconstruction, notification of startup; contents of each | Yes. |
§63.9(b)(3) | [Reserved]. | ||
§63.9(c) | Request for Compliance Extension | Can request if cannot comply by date or if installed best available control technology or lowest achievable emission rate | Yes. |
§63.9(d) | Notification of Special Compliance Requirements for New Sources | Notification for new sources subject to special compliance requirements | Yes. |
§63.9(e) | Notification of Performance Test | Notify Administrator 60 days prior | Yes. |
§63.9(f) | Notification of VE/Opacity Test | Notify Administrator 30 days prior | No. |
§63.9(g) | Additional Notifications When Using CMS | Notification of performance evaluation; notification about use of COMS data; notification that exceeded criterion for relative accuracy alternative | Yes, however, there are no opacity standards. |
§63.9(h)(1) through (3), (5), and (6) | Notification of Compliance Status | Contents due 60 days after end of performance test or other compliance demonstration, except for opacity/VE, which are due 30 days after; when to submit to Federal vs. State authority | Yes, except as specified in §63.11095(c). |
§63.9(h)(4) | [Reserved]. | ||
§63.9(i) | Adjustment of Submittal Deadlines | Procedures for Administrator to approve change when notifications must be submitted | Yes. |
§63.9(j) | Change in Previous Information | Must submit within 15 days after the change | Yes. |
§63.9(k) | Notifications | Electronic reporting procedures | Yes. |
§63.10(a) | Recordkeeping/Reporting | Applies to all, unless compliance extension; when to submit to Federal vs. State authority; procedures for owners of more than one source | Yes. |
§63.10(b)(1) | Recordkeeping/Reporting | General requirements; keep all records readily available; keep for 5 years | Yes. |
§63.10(b)(2)(i) | Records related to SSM | Recordkeeping of occurrence and duration of startups and shutdowns | No. |
§63.10(b)(2)(ii) | Records related to SSM | Recordkeeping of malfunctions | No. See §63.11094(k) for recordkeeping requirements for deviations. |
§63.10(b)(2)(iii) | Maintenance records | Recordkeeping of maintenance on air pollution control and monitoring equipment | Yes. |
§63.10(b)(2)(iv) | Records Related to SSM | Actions taken to minimize emissions during SSM | No. |
§63.10(b)(2)(v) | Records Related to SSM | Actions taken to minimize emissions during SSM | No. |
§63.10(b)(2)(vi) through (xi) | CMS Records | Malfunctions, inoperative, out-of-control periods | Yes. |
§63.10(b)(2)(xii) | Records | Records when under waiver | Yes. |
§63.10(b)(2)(xiii) | Records | Records when using alternative to relative accuracy test | Yes. |
§63.10(b)(2)(xiv) | Records | All documentation supporting initial notification and notification of compliance status | Yes. |
§63.10(b)(3) | Records | Applicability determinations | Yes. |
§63.10(c) | Records | Additional records for CMS | No. This subpart specifies CMS records. |
§63.10(d)(1) | General Reporting Requirements | Requirement to report | Yes. |
§63.10(d)(2) | Report of Performance Test Results | When to submit to Federal or State authority | No. This subpart specifies how and when the performance test results are reported. |
§63.10(d)(3) | Reporting Opacity or VE Observations | What to report and when | No. |
§63.10(d)(4) | Progress Reports | Must submit progress reports on schedule if under compliance extension | Yes. |
§63.10(d)(5) | SSM Reports | Contents and submission | No. |
§63.10(e)(1) and (2) | Additional CMS Reports | Must report results for each CEMS on a unit; written copy of CMS performance evaluation; 2-3 copies of COMS performance evaluation | No. |
§63.10(e)(3)(i) through (iii) | Reports | Schedule for reporting excess emissions | No. |
§63.10(e)(3)(iv) and (v) | Excess Emissions Reports | Requirement to revert to quarterly submission if there is an excess emissions and parameter monitor exceedances (now defined as deviations); provision to request semiannual reporting after compliance for 1 year; submit report by 30th day following end of quarter or calendar half; if there has not been an exceedance or excess emissions (now defined as deviations), report contents in a statement that there have been no deviations; must submit report containing all of the information in §§63.8(c)(7) and (8) and 63.10(c)(5) through (13) | No. |
§63.10(e)(3)(vi) through (viii) | Excess Emissions Report and Summary Report | Requirements for reporting excess emissions for CMS; requires all of the information in §§63.8(c)(7) and (8) and 63.10(c)(5) through (13) | No. |
§63.10(e)(4) | Reporting COMS Data | Must submit COMS data with performance test data | No. This subpart specifies COMS reporting. |
§63.10(f) | Waiver for Recordkeeping/Reporting | Procedures for Administrator to waive | Yes. |
§63.11(a) | Applicability | Specifies applicability of control device and work practice requirements within §63.11 | Yes. |
§63.11(b) | Flares | Requirements for flares | Yes, except these provisions no longer apply for flares used to comply with the flare provisions in item 2 of table 3 to this subpart. |
§63.11(c) through (e) | Alternative Work Practice for Monitoring Equipment for Leaks | Requirements for using optical gas imaging for EPA Method 21 monitoring | Yes, except these provisions do not apply to monitoring required under §63.11092(a)(1)(i) or (e)(1) and these provisions no longer apply upon compliance with the provisions in §63.11089(c). |
§63.12 | Delegation | State authority to enforce standards | Yes. |
§63.13 | Addresses | Addresses where reports, notifications, and requests are sent | Yes. |
§63.14 | Incorporations by Reference | Test methods incorporated by reference | Yes. |
§63.15 | Availability of Information | Public and confidential information | Yes. |
§63.16 | Performance Track Provisions | Special reporting provision for Performance Track member facilities. | Yes. |
[89 FR 39344, May 8, 2024]
Source: 73 FR 1933, Jan. 10, 2008, unless otherwise noted.
['Air Programs']
['Hazardous Air Pollutants']
UPGRADE TO CONTINUE READING
Load More
J. J. Keller is the trusted source for DOT / Transportation, OSHA / Workplace Safety, Human Resources, Construction Safety and Hazmat / Hazardous Materials regulation compliance products and services. J. J. Keller helps you increase safety awareness, reduce risk, follow best practices, improve safety training, and stay current with changing regulations.
Copyright 2025 J. J. Keller & Associate, Inc. For re-use options please contact copyright@jjkeller.com or call 800-558-5011.