10/30/2023
...
Standard Number: 1910.179
November 29, 1993
Mr. Jeffrey A. Shockey
Manager, Health & Safety
Compliance and Services Aluminum
Company of America
Alcoa Building
Pittsburgh, Pennsylvania 15219
Dear Mr. Shockey:
Thank you for your inquiries of November 2, requesting an interpretation of the Occupational Safety and Health Administration (OSHA) standard at 29 CFR 1910.179(n)(4)(i), Hoist limit switch, as it pertains to hoists that have two upper "hoist limit switches".
The OSHA standard in question requires that at the beginning of each operator's shift the upper limit switch of each hoist must be tried out under no load.
When the hoist is equipped with two upper hoist limit switches to prevent two-blocking, the first upper limit switch to be activated is the only upper hoist limit switch that needs to be tried at the beginning of each operator's shift. OSHA does not require a backup hoist limit switch.
We appreciate your interest in employee safety and health. If we can be of further assistance, please do not hesitate to contact us.
Sincerely,
Roger A. Clark, Director
Directorate of Compliance Programs
['Cranes, Lifts, and Scaffolding', 'Materials Handling and Storage']
['Overhead Cranes', 'Materials Handling and Storage']
UPGRADE TO CONTINUE READING
Load More
J. J. Keller is the trusted source for DOT / Transportation, OSHA / Workplace Safety, Human Resources, Construction Safety and Hazmat / Hazardous Materials regulation compliance products and services. J. J. Keller helps you increase safety awareness, reduce risk, follow best practices, improve safety training, and stay current with changing regulations.
Copyright 2025 J. J. Keller & Associate, Inc. For re-use options please contact copyright@jjkeller.com or call 800-558-5011.