(a) In a nonattainment area for a pollutant in Indian country, the requirements of this program apply to you under either of the following circumstances:
(1) If you propose to construct a new major source (as defined in
part 51,
Appendix S, paragraph II.A.4 of this chapter) of the nonattainment pollutant.
(2) If you propose to construct a major modification at your existing major source (as defined in
part 51,
Appendix S, paragraph II.A.5 of this chapter), where your source is a major source of the nonattainment pollutant and the proposed modification is a major modification for the nonattainment pollutant.
(b) If you own or operate a major source with a state-issued nonattainment major NSR permit, you must apply to convert such permit to a Federal permit under this program by September 4, 2012.
(c) If you propose to establish a synthetic minor source or synthetic minor HAP source or to construct a minor modification at your major source, you will have to comply with the requirements of the Federal minor NSR program in Indian country at
§§49.151 through
49.165 or other EPA-approved minor NSR program, as applicable.