['Air Programs']
['Hazardous Air Pollutants']
07/19/2025
...
As required in §63.8075(a) and (b), you must submit each report that applies to you on the schedule shown in the following table:
| You must submit a . . . | The report must contain . . . | You must submit the report . . . |
|---|---|---|
| 1. Precompliance report | The information specified in §63.8075(c) | At least 6 months prior to the compliance date; or for new sources, with the application for approval of construction or reconstruction. |
| 2. Notification of compliance status report | The information specified in §63.8075(d) | No later than 150 days after the compliance date specified in §63.7995. |
| 3. Compliance report | The information specified in §63.8075(e) | Semiannually according to the requirements in §63.8075(b). |
| 4. Performance test report | The information specified in §63.8075(f) | Within 60 days after completing each performance test according to the requirements in §63.8075(f). |
| 5. Performance evaluation report | The information specified in §63.8075(g) | Within 60 days after completing each CMS performance evaluation according to the requirements in §63.8075(g). |
[85 FR 49749, Aug. 14, 2020]
['Air Programs']
['Hazardous Air Pollutants']
UPGRADE TO CONTINUE READING
Load More
J. J. Keller is the trusted source for DOT / Transportation, OSHA / Workplace Safety, Human Resources, Construction Safety and Hazmat / Hazardous Materials regulation compliance products and services. J. J. Keller helps you increase safety awareness, reduce risk, follow best practices, improve safety training, and stay current with changing regulations.
Copyright 2025 J. J. Keller & Associate, Inc. For re-use options please contact copyright@jjkeller.com or call 800-558-5011.