Reference | Applies to subparts F, G and H | Comment |
---|---|---|
a Wherever subpart A specifies “postmark” dates, submittals may be sent by methods other than the U.S. Mail (e.g., by fax or courier). Submittals shall be sent by the specified dates, but a postmark is not necessarily required.
b The plan, and any records or reports of start-up, shutdown, and malfunction do not apply to Group 2 emission points unless they are included in an emissions average. | ||
63.1(a)(1) | Yes | Overlap clarified in §63.101, §63.111, §63.161. |
63.1(a)(2) | Yes | |
63.1(a)(3) | Yes | §63.110 and §63.160(b) of subparts G and H identify which standards are overridden. |
63.1(a)(4) | No | Subpart F specifies applicability of each paragraph in subpart A to subparts F, G and H. |
63.1 (a)(5)-(a)(9) | No | |
63.1(a)(10) | No | Subparts F, G and H specify calendar or operating day. |
63.1(a)(11) | No | Subpart F §63.103(d) specifies acceptable methods for submitting reports. a |
63.1 (a)(12)-(a)(14) | Yes | |
63.1(b)(1) | No | Subpart F specifies applicability. |
63.1(b)(2) | Yes | |
63.1(b)(3) | No | |
63.1(c)(1) | No | Subpart F specifies applicability. |
63.1(c)(2) | No | Area sources are not subject to subparts F, G and H. |
63.1(c)(3) | No | |
63.1(c)(4) | Yes | |
63.1(c)(5) | No | Subparts G and H specify applicable notification requirements. |
63.1(c)(6) | Yes | |
63.1(d) | No | |
63.1(e) | No | Subparts F, G and H established before permit program. |
63.2 | Yes | Subpart F §63.101(a) specifies those subpart A definitions that apply to the HON. Subpart F definition of “source” is equivalent to subpart A definition of “affected source.” |
63.3 | No | Units of measure are spelled out in subparts F, G and H. |
63.4 (a)(1)-(a)(3) | Yes | |
63.4(a)(4) | No | This is a reserved paragraph in subpart A of part 63. |
63.4(a)(5) | Yes | |
63.4(b) | Yes | |
63.4(c) | Yes | |
63.5(a)(1) | Yes | Except the terms “source” and “stationary source” in §63.5(a)(1) should be interpreted as having the same meaning as “affected source.” |
63.5(a)(2) | Yes | |
63.5(b)(1) | Yes | Except §63.100(l) defines when construction or reconstruction is subject to standards for new sources. |
63.5(b)(2) | No | This is a reserved paragraph in subpart A of part 63. |
63.5(b)(3) | Yes | |
63.5(b)(4) | Yes | Except the cross reference to §63.9(b) is limited to §63.9(b) (4) and (5). Subpart F overrides §63.9 (b)(1) through (b)(3). |
63.5(b)(5) | Yes | |
63.5(b)(6) | Yes | Except §63.100(l) defines when construction or reconstruction is subject to standards for new sources. |
63.5(c) | No | This is a reserved paragraph in subpart A of part 63. |
63.5(d)(1)(i) | No | For subpart G, see §63.151(b) (2)(ii) and (2)(iii) for the applicability and timing of this submittal; for subpart H, see §63.182(b) (2)(ii) and (b)(2)(iii) for applicability and timing of this submittal. |
63.5(d)(1)(ii) | Yes | Except §63.5(d)(1)(ii)(H) does not apply. |
63.5(d)(1)(iii) | No | Subpart G requires submittal of the Notification of Compliance Status in §63.152(b); subpart H specifies requirements in §63.182(c). |
63.5(d)(2) | No | |
63.5(d)(3) | Yes - subpart G No - subpart H | Except §63.5(d)(3)(ii) does not apply to subpart G. |
63.5(d)(4) | Yes | |
63.5(e) | Yes | |
63.5(f)(1) | Yes | |
63.5(f)(2) | Yes | Except the cross-reference to §63.5(d)(1) is changed to §63.151(b)(2)(ii) of subpart G and to §63.182(b)(2)(ii) of subpart H. The cross-reference to §63.5(b)(2) does not apply. |
63.6(a) | Yes | |
63.6(b)(1) | No | Subparts F and H specify compliance dates for sources subject to subparts F, G and H. |
63.6(b)(2) | No | |
63.6(b)(3) | Yes | |
63.6(b)(4) | No | May apply when standards are proposed under Section 112(f) of the Clean Air Act. |
63.6(b)(5) | No | Subparts G and H include notification requirements. |
63.6(b)(6) | No | |
63.6(b)(7) | No | |
63.6(c)(1) | No | Subpart F specifies the compliance dates for subparts G and H. |
63.6(c)(2) | No | |
63.6(c)(3) | No | |
63.6(c)(4) | No | |
63.6(c)(5) | Yes | |
63.6(d) | [Reserved] | |
63.6(e) | Yes c | Except as otherwise specified for individual paragraphs. Does not apply to Group 2 emission points unless they are included in an emissions average. bc |
63.6(e)(1)(i) | No | This is addressed by §63.102(a)(4) and (f) of subpart F. |
63.6(e)(1)(ii) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.6(e)(1)(iii) | Yes | |
63.6(e)(2) | [Reserved] | |
63.6(e)(3)(i) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.6(e)(3)(i)(A) | No | This is addressed by §63.102(a)(4). |
63.6(e)(3)(i)(B) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.6(e)(3)(i)(C) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.6(e)(3)(ii) | [Reserved] | |
63.6(e)(3)(iii) | No | Recordkeeping and reporting are specified in §63.103(c)(2) of subpart F and §63.152(d)(1) of subpart G. |
63.6(e)(3)(iv) | No | Recordkeeping and reporting are specified in §63.103(c)(2) of subpart F and §63.152(d)(1) of subpart G. |
63.6(e)(3)(v) | No | Records retention requirements are specified in §63.103(c). |
63.6(e)(3)(vi) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.6(e)(3)(vii) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.6(e)(3)(viii) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.6(e)(3)(ix) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.6(f)(1) | No | §63.102(a) and (e) of subpart F specifies when the standards apply. |
63.6(f)(2)(i) | Yes | |
63.6(f)(2)(ii) | Yes - subpart G No - subpart H | §63.152(c)(2) of subpart G specifies the use of monitoring data in determining compliance with subpart G. |
63.6(f)(2)(iii) (A), (B), and (C) | Yes | |
63.6(f)(2)(iii)(D) | No | |
63.6(f)(2)(iv) | Yes | |
63.6(f)(2)(v) | Yes | |
63.6(f)(3) | Yes | |
63.6(g) | No | Procedures specified in §63.102(b) of subpart F. |
63.6(h) | No | |
63.6(i)(1) | Yes | |
63.6(i)(2) | Yes | |
63.6(i)(3) | No | For subpart G, §63.151(a)(6) specifies procedures; for subpart H, §63.182(a)(6) specifies procedures. |
63.6(i)(4)(i)(A) | Yes | |
63.6(i)(4)(i)(B) | No | Dates are specified in §63.151(a)(6)(i) of subpart G and §63.182(a)(6)(i) of subpart H. |
63.6(i)(4)(ii) | No | |
63.6(i) (5)-(14) | Yes | |
63.6(i)(15) | No | |
63.6(i)(16) | Yes | |
63.6(j) | Yes | |
63.7(a)(1) | No | Subparts F, G and H specify required testing and compliance demonstration procedures. |
63.7(a)(2) | No | For subpart G, test results must be submitted in the Notification of Compliance Status due 150 days after compliance date, as specified in §63.152(b); for subpart H, all test results subject to reporting are reported in periodic reports. |
63.7(a)(3) | Yes | |
63.7(a)(4) | Yes | |
63.7(b) | No | |
63.7(c) | No | |
63.7(d) | Yes | |
63.7(e)(1) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | See §63.103(b)(3). |
63.7(e)(2) | Yes | |
63.7(e)(3) | No | Subparts F, G and H specify test methods and procedures. |
63.7(e)(4) | Yes | |
63.7(f) | Yes | |
63.7(g) | No | Performance test reporting specified in §63.152(b) of subpart G: Not applicable to subpart H because no performance test required by subpart H. |
63.7(h)(1) | Yes | |
63.7(h)(2) | Yes | |
63.7(h)(3) | No | §63.103(b)(5) of subpart F specifies provisions for requests to waive performance tests. |
63.7(h)(4) | No | |
63.7(h)(5) | Yes | |
63.8(a)(1) | Yes | |
63.8(a)(2) | No | |
63.8(a)(3) | [Reserved] | |
63.8(a)(4) | Yes, except for flares subject to §63.108 | |
63.8(b)(1) | Yes | |
63.8(b)(2) | No | Subparts G and H specify locations to conduct monitoring. |
63.8(b)(3) | Yes | |
63.8(c)(1)(i) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.8(c)(1)(ii) | No | For subpart G, submit as part of periodic report required by §63.152(c); for subpart H, retain as required by §63.181(g)(2)(ii). |
63.8(c)(1)(iii) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | |
63.8(c)(2) | Yes | |
63.8(c)(3) | Yes | |
63.8(c)(4) | No | Subpart G specifies monitoring frequency by kind of emission point and control technology used (e.g., §63.111, §63.120(d)(2), §63.143, and §63.152(f)); subpart H does not require use of continuous monitoring systems. |
63.8 (c)(5)-(c)(8) | No | |
63.8(d) | No | |
63.8(e) | No | |
63.8 (f)(1)-(f)(3) | Yes | |
63.8(f)(4)(i) | No | Timeframe for submitting request specified in §63.151(f) or (g) of subpart G; not applicable to subpart H because subpart H specifies acceptable alternative methods. |
63.8(f)(4)(ii) | Yes | |
63.8(f)(4)(iii) | No | |
63.8(f)(5)(i) | Yes | |
63.8(f)(5)(ii) | No | |
63.8(f)(5)(iii) | Yes | |
63.8(f)(6) | No | Subparts G and H do not require continuous emission monitoring. |
63.8(g) | No | Data reduction procedures specified in §63.152(f) and (g) of subpart G; not applicable to subpart H. |
63.9(a) | Yes | |
63.9(b)(1) | No | Specified in §63.151(b)(2) of subpart G; specified in §63.182(b) of subpart H. |
63.9(b)(2) | No | Initial Notification provisions are specified in §63.151(b) of subpart G; in §63.182(b) of subpart H. |
63.9(b)(3) | No | |
63.9(b)(4) | Yes | Except that the notification in §63.9(b)(4)(i) shall be submitted at the time specified in §63.151(b)(2)(ii) of subpart G; in §63.182(b)(2) of subpart H. |
63.9(b)(5) | Yes | Except that the notification in §63.9(b)(5) shall be submitted at the time specified in §63.151(b)(2)(ii) of subpart G; in §63.182 (b)(2) of subpart H. |
63.9(c) | Yes | |
63.9(d) | Yes | |
63.9(e) | No | |
63.9(f) | No | |
63.9(g) | No | |
63.9(h) | No | §63.152(b) of subpart G and §63.182 (c) of subpart H specify Notification of Compliance Status requirements. |
63.9(i) | Yes | |
63.9(j) | Yes | Only as related to change to major source status. |
63.9(k) | Yes | |
63.10(a) | Yes | |
63.10(b)(1) | No | §63.103(c) of subpart F specifies record retention requirements. |
63.10(b)(2) | No | §63.103(c) of subpart F specifies required records. |
63.10(b)(3) | No | |
63.10(c) | No | |
63.10(d)(1) | No | |
63.10(d)(2) | No | §63.152(b) of subpart G specifies performance test reporting; not applicable to subpart H. |
63.10(d)(3) | No | |
63.10(d)(4) | Yes | |
63.10(d)(5) | Yes, before July 15, 2027. No, beginning on and after July 15, 2027 | Except that, before July 15, 2027, reports required by §63.10(d)(5) shall be submitted at the time specified in §63.152(d) of subpart G and in §63.182(d) of subpart H. |
63.10(e) | No | |
63.10(f) | Yes | |
63.11-63.15 | Yes, except 63.11(b) does not apply to flares subject to §63.108 |
[62 FR 2737, Jan. 17, 1997, as amended at 71 FR 20456, Apr. 20, 2006; 85 FR 73887, Nov. 19, 2020; 89 FR 43067, May 16, 2024]
['Air Programs']
['Hazardous Air Pollutants']
Load More
J. J. Keller is the trusted source for DOT / Transportation, OSHA / Workplace Safety, Human Resources, Construction Safety and Hazmat / Hazardous Materials regulation compliance products and services. J. J. Keller helps you increase safety awareness, reduce risk, follow best practices, improve safety training, and stay current with changing regulations.
Copyright 2024 J. J. Keller & Associate, Inc. For re-use options please contact copyright@jjkeller.com or call 800-558-5011.