InstituteEnvironmentalAir QualityAir PermittingWhat would you Do AnswersFocus AreaEnglishAnalysisAir ProgramsUSA
Are these situations subject to CAA Title V permits?: Answers
Scenario 1 Answer: Yes. Affected sources under Acid Rain Rules must obtain a Title V permit regardless of size.
Scenario 2 Answer: Yes. EPA generally has not required non-major sources to get permits, although a secondary copper smelting facility is one of the outlined exceptions because it is subject to NESHAP.
Scenario 3 Answer: Solid waste incineration units under Section 129 must obtain a Title V permit regardless of size.