(a) If your new unit subject to this subpart is applying for a permit the first time, a complete title V permit application must be submitted timely either 12 months after the date the unit commences operation as a new source or before one of the dates specified in paragraph (b) of this section, as applicable.
(b) For a unit that commenced operation as a new source as of December 16, 2005, then a complete title V permit application must be submitted not later than December 18, 2006. For a small OSWI unit that commenced operation as a new source as of April 17, 2024, a complete title V permit application must be submitted not later than April 18, 2025.
(c) [Reserved]
[89 FR 27392, April 17, 2024]